INSP-Final Inspection | 2/28/2013 | 3/1/2013 | 3/1/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2013 | 3/1/2013 | 2/28/2013 | P | CANC |
Troy Cobbley
|
|
|
Trent Bice is contact at ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Final Inspection | 2/28/2013 | 3/1/2013 | 2/28/2013 | A | CANC |
Troy Cobbley
|
|
|
Please contact Trent Bice at ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Final Inspection | 2/25/2013 | 2/26/2013 | 2/26/2013 | A | FAIL |
Troy Cobbley
|
|
|
All items are complete except for the verification of the interconnection with the fire alarm system.
|
INSP-Conference | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | DONE |
Troy Cobbley
|
|
|
I went over outstanding fire alarm items with Chris, the job superintendant. It appears that many of the devices are not connected to the fire alarm panel yet. They include 120 volt smoke alarms, hood suppression system, flow switch, tamper switches..ect. The fire alarm system has not been scheduled yet for an inspection.
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2013 | 2/19/2013 | 2/19/2013 | A | PASS |
Troy Cobbley
|
|
|
The previous correction items have been addressed. For this permit to be finaled the ceiling needs to be finished/installed in the kitchen, ceilings painted so the canopies can be installed and the fire alarm interconnections tested. Currently the fire alarm system is not connected to the sprinkler devices.
|
INSP-Sprinkler Rough-in | 2/15/2013 | 2/15/2013 | 2/15/2013 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for locations where a wall in the attic needs to be removed or additional coverage provided. Also BB heads need to be added in two locations due to overspacing from walls. One pendant head in a shower is too close to a wall and anothe pendant head needs to be added in the riser room due to a wall, not shown on the plans, blocking coverage. Per trent different residential pendants are being used. I requested that he have them approved by tim prior to a final.
|
INSP-Sprinkler Rough-in/Hydro | 2/4/2013 | 2/5/2013 | 2/5/2013 | A | PASS |
Troy Cobbley
|
|
|
The overhead and underground hydro tests passed. One leaking head was tightened while I waited.
|
INSP-Supply line flush | 1/11/2013 | 1/14/2013 | 1/14/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Supply line flush | 12/20/2012 | 12/26/2012 | 12/26/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per text from Brian due to United Water.
|
INSP-Sprinkler Rough-in | 12/20/2012 | 12/21/2012 | 12/21/2012 | A | PART |
Forrest France
|
|
|
Remainder of the underground fire supply line including the ductile stub-in are approved for bury. See plans for dated annotations.
|
INSP-Sprinkler Rough-in | 12/18/2012 | 12/18/2012 | 12/18/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new location where the under ground supply line can now be covered.
|
INSP-Sprinkler Rough-in | 12/14/2012 | 12/14/2012 | 12/14/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional underground supply piping that is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location of partial underground inspection where the piping is ok to cover.
|