INSP-Final Inspection | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 7/1/2014 | 7/2/2014 | 7/2/2014 | A | PASS |
Troy Cobbley
|
|
|
The fire alarm in Phase III (Med Lab) is complete.
|
INSP-Alarm Testing | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | DONE |
Troy Cobbley
|
|
|
Need two fire smoke dampers adjusted. before sign off in the remodeled area.
|
INSP-Alarm Testing | 6/30/2014 | 6/30/2014 | 6/30/2014 | P | DONE |
Troy Cobbley
|
|
|
Additional area in the remodeled ER area passed. Need two smoke detectors relocated to the center line of the doors and with-in 5'
|
INSP-Alarm Testing | 5/14/2014 | 5/14/2014 | 5/14/2014 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm devices in the temporary corridor in the remodeled ER area have been tested and passed
|
INSP-Alarm Testing | 5/7/2014 | 5/8/2014 | 5/8/2014 | A | PART |
Troy Cobbley
|
|
|
Inspection was for temporary corridor through the ER area. All items tested ok but one additional notification device is needed at the east end bdfore I can give an "ok" for use.
|
INSP-Alarm Testing | 12/26/2013 | 12/27/2013 | 12/27/2013 | A | PART |
Troy Cobbley
|
|
|
Fire alarm complete in 2B and Staff Lounge.
|
INSP-Alarm Testing | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | DONE |
Craig D. Hanson
|
|
|
Phase 2A; All systems tested and pass for this phase. Initiating devices + 4 pull stations and 1 duct detector.
|
INSP-Alarm Testing | 9/6/2013 | 9/6/2013 | 9/6/2013 | P | CANC |
Troy Cobbley
|
|
|
Call prior to going Phone #: 2089411846 >> Inspection requested via mobile web by Brian Anderson Inspection cancelled via mobile web on Friday, September 06, 2013.
|
INSP-Alarm Testing | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | DONE |
Troy Cobbley
|
|
|
Phase one fire alarm passed. Door release has been corrected and a weather proof device added in the "decontam" room. Brian is going to keep the updated as-builts on his Ipad.
|
INSP-Alarm Testing | 3/5/2013 | 3/6/2013 | 3/7/2013 | P | PART |
Forrest France
|
|
|
Functional testing and inspection for fire alarm work in "phase one" completed. Noted items include; provide a WP notification appliance in the decontamination room, address at SD's for door release (22 &23) are switched, SD and ID at the south set of hallway doors between phase one and two are not yet installed, ID M8-13 has been relocated to the main corridor beyond phase one, delayed egress provisions at the secured doors must meet conditions per IFC 2009, record drawings and panel maps to match field modifications including device locations and addressing. Chimes/strobes, MP at the nurses station, SD and ID(except as noted) tested okay. *Inspection completed 3/6/13 PM*.
|