INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
Noted unfinished circulation, lobby and corridor areas.
|
INSP-Final Inspection | 11/27/2013 | 11/29/2013 | 11/29/2013 | A | DEFR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus *inspection intended for 12/2
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/1/2013 | 11/4/2013 | 11/5/2013 | P | PART |
Forrest France
|
|
|
Inspection for drops at the grid ceiling above the escalator.
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
2nd floor hydrostatic test of the shell fire protection system passed.
|
INSP-Sprinkler Rough-in | 3/4/2013 | 3/6/2013 | 3/6/2013 | A | PART |
Forrest France
|
|
|
Rough-in at the second floor completed. Discussed shell/TI schedule, hydrostatic test procedures, floor control manifold/PRV isolation valves per the mfg. data sheets and approved plans.
|