INSP-Final Inspection | 1/7/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 1/6/2014 | 1/6/2014 | 1/6/2014 | A | PART |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PART |
Forrest France
|
|
|
Final pending trip times at dry systems floor levels 3, 4, and 5 per plan review notes item #2 and alternate agreement letter.
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
Refer to fire plan review note # 2 regarding alternate agreement for trip times at the dry systems. C/N items noted at floors 7,8,9, and 12..
|
INSP-Final Inspection | 11/27/2013 | 12/2/2013 | 12/3/2013 | A | PART |
Forrest France
|
|
|
Completed trip testing for new dry systems at the 3rd, 4th, and 5th floor parking garage levels. Also noted obstructed upright coverage at the service elevator lobbies typical most floors 6-15, missing hangers on mains parallel to and beneath stairways, temporary construction office at the NE corner of the 10th floor disrupts shell coverage. Final shell walkthrough incomplete at this time.
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Conference | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | DONE |
Forrest France
|
|
|
Regarding upright coverage at the mechanical penthouse.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2013 | 4/25/2013 | 5/2/2013 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test at floors 11 -15 completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2013 | 4/8/2013 | 4/12/2013 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/3/2013 | 4/3/2013 | 4/3/2013 | P | PART |
Forrest France
|
|
|
Regarding noted C/N items
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
OH hydrostatic test of the 3rd, 4th, and 5th floor dry systems completed satisfactory. Also finished hydrostatic tests of shell system work at the 6th -10th floor levels.
|
INSP-Sprinkler Rough-in | 3/20/2013 | 3/21/2013 | 3/22/2013 | A | PART |
Forrest France
|
|
|
Shell work at the 9th, 10th, and 11th floors inspected today- noted items include overspaced head at the 9th floor restroom, ssu at south duct needs adjustment, missing hangers at 11th floor arm-overs.
|
INSP-Sprinkler Rough-in | 3/18/2013 | 3/18/2013 | 3/21/2013 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 3/14/2013 | 3/15/2013 | 3/15/2013 | A | PART |
Forrest France
|
|
|
Completed shell fire protection rough-in at floors 7 and 8. Noted missing hangers at floor 8, beam obstruction at the fire service elevator lobby typical per floor.
|
INSP-Sprinkler Rough-in | 3/13/2013 | 3/14/2013 | 3/14/2013 | P | PART |
Forrest France
|
|
|
6th floor rough-in completed. Noted missing coverage at the SE corner, beam obstruction at the fire service elevator lobby.
|
INSP-Sprinkler Rough-in | 3/6/2013 | 3/8/2013 | 3/13/2013 | A | PART |
Forrest France
|
|
|
Refer to stamped plan set regarding 3rd floor rough-in correction items including spacing, obstructions, field changes, incompleted piping due to construction underway, hangers, coverage at the electrical room.
|
INSP-Final Inspection | 1/2/2014 | 1/2/2014 | | P | |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/11/2013 | 3/12/2013 | | P | |
Forrest France
|
|
|
This is for the 3rd, 4th & 5th Fl. Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|