INSP-Final Inspection | 6/3/2013 | 6/4/2013 | 6/4/2013 | P | PASS |
Forrest France
|
|
|
Remainder of correction items verified for completion, final walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 5/30/2013 | 6/3/2013 | 6/3/2013 | A | PART |
Forrest France
|
|
|
Walkthrough completed, final pending coverage adjustments at the "green room" due to surface mounted obstructions.
|
INSP-Final Inspection | 5/24/2013 | 5/28/2013 | 5/28/2013 | P | NH |
Forrest France
|
|
|
No access to complete inspection due to epoxy floor finishes underway.
|
INSP-Final Inspection | 5/23/2013 | 5/24/2013 | 5/24/2013 | A | NR |
Forrest France
|
|
|
Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/17/2013 | 5/20/2013 | 5/20/2013 | A | PART |
Forrest France
|
|
|
Previous correction items verified for completion. Plan modification work okayed for cover at the new grid ceilings. Final pending replacement of painted heads in the lobby, meeting room and sanctuary/stage areas, ceiling tile and escutcheons not yet installed. Noted one upright head at the mechanical mezzanine to be relocated. Outside waterflow bell repaired while on site.
|
INSP-Final Inspection | 5/16/2013 | 5/17/2013 | 5/17/2013 | A | NR |
Forrest France
|
|
|
Mark J is the contact Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus * Plans currently in "review" status.
|
INSP-Sprinkler Rough-in | 5/16/2013 | 5/17/2013 | 5/17/2013 | A | NR |
Forrest France
|
|
|
Mark J is the contact Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus * Plans currently in "review" status.
|
INSP-Sprinkler Rough-in | 5/13/2013 | 5/14/2013 | 5/14/2013 | P | PART |
Forrest France
|
|
|
Refer to clouded, initialed and dated locations on approved plan set for grid ceiling rooms and areas okayed for cover. Noted three missing uprights and one missing hanger above two rooms. Several areas now have grid ceilings where plans indicate open to structure. Painted upright heads will need to be replaced per NFPA 13 requirements.
|
INSP-Sprinkler Rough-in | 4/18/2013 | 4/19/2013 | 4/19/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" in red where sprinkler piping can be covered
|