INSP-Final Inspection | 4/14/2015 | 4/15/2015 | 4/14/2015 | A | PASS |
Katie Marron
|
|
|
Final walk through completed. Verified functional flow switch. Contractor to replace missing echeons/patch hole at mechanical closets adjacent to riser room, and to post sign at riser room door per review notes.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2015 | 4/14/2015 | 4/14/2015 | P | DEFR |
Katie Marron
|
|
|
Wrong inspection type, request intended for final.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2015 | 4/13/2015 | 4/7/2015 | P | CANC |
Forrest France
|
|
|
Ken to Attend Phone #: ###-#### >> Inspection requested via web by Connie Danes Inspection cancelled from web by: Connie Danes
|
INSP-Sprinkler Rough-in | 5/2/2013 | 5/3/2013 | 5/3/2013 | A | PART |
Forrest France
|
|
|
Inspection for cold cavity protection completed satisfactory. One area second floor east bedroom adjusted while on site. Verified piping to pendent head below the intermediate stair landing. Overhead work okay to cover.
|
INSP-Sprinkler Rough-in | 4/22/2013 | 4/23/2013 | 4/23/2013 | A | PART |
Forrest France
|
|
|
Overhead rough-in completed. Cover approval pending verification of cold cavity protection when installed. Missing coverage below the upper stair landing, riser is not yet built, DP at the garage are on order.
|
INSP-Sprinkler Rough-in | 4/10/2013 | 4/11/2013 | 4/12/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line approved for bury
|