INSP-Final Inspection | 3/19/2014 | 3/19/2014 | 3/19/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2014 | 3/19/2014 | 3/19/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 11/21/2013 | 11/22/2013 | 11/22/2013 | A | PASS |
Troy Cobbley
|
|
|
underground flush passed
|
INSP-Supply line flush | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | PASS |
Troy Cobbley
|
|
|
ug flush passed
|
INSP-Sprinkler Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PASS |
Troy Cobbley
|
|
|
underground flush bld 15 passed
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2013 | 9/11/2013 | 9/11/2013 | A | PASS |
Troy Cobbley
|
|
|
hydro bldg 12 passed ; flush bldg 14 passed
|
INSP-Sprinkler Rough-in | 8/7/2013 | 8/8/2013 | 8/8/2013 | P | PASS |
Troy Cobbley
|
|
|
Building 12 underground supply piping is ok to cover with the understanding that the plans will need to be resubmitted to show the connection and routing changes.
|
INSP-Sprinkler Rough-in | 8/7/2013 | 8/7/2013 | 8/7/2013 | P | PASS |
Troy Cobbley
|
|
|
undergroung piping is ok to cover from the United Water connection to the 90 and then 51' along the building. Plan modifications are needed showing the complete routing change and point of connection changes.
|
INSP-Sprinkler Rough-in | 7/22/2013 | 7/23/2013 | 7/23/2013 | P | PASS |
Troy Cobbley
|
|
|
ug for bldg 15 & 13 is ok to cover. See the city approved plans for locations.
|
INSP-Sprinkler Rough-in | 7/8/2013 | 7/8/2013 | 7/8/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the underground that has been clouded and with todays date that is ok to cover.
|