INSP-Final Inspection | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | PASS |
Craig D. Hanson
|
|
|
Completed overhead and hydro/ ball drip added.
|
INSP-Sprinkler Rough-in | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | FAIL |
Craig D. Hanson
|
|
|
Tenting of pipe pass o sprinkler head on 1st floor West unit W bedroom still to far off wall.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2013 | 9/6/2013 | 9/6/2013 | P | PART |
Troy Cobbley
|
|
|
There are two overspaced pendants and one that still needs to be installed. See red lines on plans.Tim is ok with coverage in the commonn stair well due to rated assembley. The extended coverage sidewall has not been installed yet. Riser has not been built. Tenting has not been done yet.
|
INSP-Supply line flush | 9/5/2013 | 9/6/2013 | 9/6/2013 | A | PART |
Troy Cobbley
|
|
|
Underground flush passed. Will have to be redone if the underground supply nees to be repaired.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2013 | 9/6/2013 | 9/6/2013 | A | FAIL |
Troy Cobbley
|
|
|
Ug hydro failed due visable pressure loss on guage.
|
INSP-Sprinkler Rough-in | 8/7/2013 | 8/7/2013 | 8/7/2013 | P | PASS |
Troy Cobbley
|
|
|
This was an ug rough in. The 2" poly supply piping is ok to cover up to the United Water connection point at the existing water meter.
|