INSP-Final Inspection | 12/5/2013 | 12/6/2013 | 12/6/2013 | P | PASS |
Craig D. Hanson
|
|
|
No corrections
|
INSP-Supply line flush | 11/21/2013 | 11/21/2013 | 11/21/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 11/11/2013 | 11/12/2013 | 11/12/2013 | P | CANC |
Troy Cobbley
|
|
|
Underground hydro is not required.
|
INSP-Sprinkler Rough-in | 10/21/2013 | 10/21/2013 | 10/21/2013 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Tenting is approved. I noted two heads located less than the required 8'. Change will be verified at the final.
|
INSP-Sprinkler Rough-in | 8/19/2013 | 8/20/2013 | 8/20/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover. Piping is 2" poly like the others.
|
INSP-Sprinkler Rough-in | 8/16/2013 | 8/19/2013 | 8/19/2013 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
|