INSP-Final Inspection | 11/4/2013 | 11/6/2013 | 11/6/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/4/2013 | 11/5/2013 | 11/4/2013 | P | CANC |
Troy Cobbley
|
|
|
James is the contact. THanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 11/1/2013 | 11/4/2013 | 11/4/2013 | P | CANC |
Troy Cobbley
|
|
|
James Raff is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 9/26/2013 | 9/26/2013 | 9/26/2013 | P | PASS |
Troy Cobbley
|
|
|
Rough-in inspection passed. Tenting inspection passed. Piping can be covered.
|
INSP-Supply line flush | 9/26/2013 | 9/26/2013 | 9/26/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 9/24/2013 | 9/25/2013 | 9/25/2013 | A | FAIL |
Troy Cobbley
|
|
|
No inspection performed due to the pipe routing not matching the approved plans. Contractor shall contact the plan reviewer to verify if plan modifications are required due to changed hydraulic calculations or if as-builts can be acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro tests passed
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2013 | 9/18/2013 | 9/18/2013 | P | PART |
Troy Cobbley
|
|
|
Hydro test passed for the underground but failed on both overhead systems due to visible pressure loss at the guages
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2013 | 9/18/2013 | 9/18/2013 | A | CANC |
Troy Cobbley
|
|
|
This is for an ug & oh hydro. Mike Rogers is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground is ok to cover.
|