INSP-Final Inspection | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/13/2014 | 1/13/2014 | 1/14/2014 | P | PART |
Forrest France
|
|
|
Previous corrections verified for completion. Final pending drop ceiling and finishes at the meeting room.
|
INSP-Final Inspection | 1/7/2014 | 1/10/2014 | 1/10/2014 | P | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/2/2014 | 1/3/2014 | 1/3/2014 | A | PART |
Forrest France
|
|
|
Inspection for cover at the grid ceiling areas completed- Noted three heads to be relocated due to proximity to heat diffusers, one head blocked by a pendent mounted light fixture, adjustment to coverage at a closet. Discussed ceiling finishes at a conference room.
|
INSP-Sprinkler Rough-in | 11/8/2013 | 11/12/2013 | 11/12/2013 | P | PART |
Craig D. Hanson
|
|
|
Cover for lids in Zion Bank area. pass.
|