INSP-Final Inspection | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | PASS |
Forrest France
|
|
|
Okay to final UG fire supply line permit.
|
INSP-Supply line flush | 1/30/2014 | 1/30/2014 | 1/31/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2013 | 12/16/2013 | 12/17/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic testing completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2013 | 12/9/2013 | 12/9/2013 | A | CANC |
Troy Cobbley
|
|
|
UG hydro canceled due to cold temperatures per troy
|
INSP-Supply line flush | 11/19/2013 | 11/21/2013 | 11/21/2013 | A | PART |
Forrest France
|
|
|
Remainder of UG fire supply line including thrust blocking prior to tie-in okayed for cover.
|
INSP-Sprinkler Rough-in | 11/14/2013 | 11/14/2013 | 11/14/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover. 8" run along the street will need to have fill nearly level with the street to meet the 4'6" bury requirement.
|
INSP-Sprinkler Rough-in | 9/19/2013 | 9/19/2013 | 9/19/2013 | P | PART |
Forrest France
|
|
|
IBR only okayed for cover
|