INSP-Final Inspection | 9/22/2014 | 9/23/2014 | 9/23/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PART |
Forrest France
|
|
|
Completed walkthrough of 2nd floor core and common areas including restrooms for fire sprinkler finishes. Verified added coverage at 2" CPVC main.
|
INSP-Final Inspection | 7/3/2014 | 7/7/2014 | 7/7/2014 | A | PART |
Forrest France
|
|
|
Completed walkthrough for fire sprinkler finishes at the 1st floor core, lobby, reception, and common areas. Missing escutcheon replaced while on site, verified outside waterflow bell. Need to provide coverage at a closet or meet exceptions per NFPA 13.
|
INSP-Sprinkler Rough-in | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | PART |
Forrest France
|
|
|
Inspection for 2nd floor west lobby, north lobby and core area grid ceilings passed rough-in, okayed for cover. Need to provide upright protection at the exposed 2" CPVC feed main (apartments) located in the future office shell area.
|
INSP-Final Inspection | 7/1/2014 | 7/2/2014 | 7/2/2014 | P | PART |
Forrest France
|
|
|
Verified seismic bracing at the basement level 2 1/2" main north side.
|
INSP-Final Inspection | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PART |
Forrest France
|
|
|
Inspection for scope of work at the basement level. Discussed seismic bracing, standard response heads, pump layout, added and relocated sprinkler coverage.
|
INSP-Final Inspection | 6/30/2014 | 6/30/2014 | 7/1/2014 | P | PART |
Forrest France
|
|
|
Completed walkthrough for the 7th floor overhead finish work.
|
INSP-Sprinkler Rough-in | 6/30/2014 | 6/30/2014 | 7/1/2014 | P | PART |
Forrest France
|
|
|
Terry-basement floor only please Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | NR |
Forrest France
|
|
|
2nd floor corridior rough-in not ready for inspection due to painting underway.
|
INSP-Sprinkler Rough-in | 6/18/2014 | 6/19/2014 | 6/19/2014 | A | PART |
Forrest France
|
|
|
2nd floor storage room, bride room and hallway as dated on plans passed rough-in pending approved plan mod reflecting field changes.
|
INSP-Sprinkler Rough-in | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PART |
Forrest France
|
|
|
!st floor main at entry vestibule, 2nd floor girid ceiling above west stairway as marked and dated on plans approved for cover.
|
INSP-Sprinkler Rough-in | 6/13/2014 | 6/13/2014 | 6/13/2014 | P | PART |
Forrest France
|
|
|
EC heads at the banquet room 1st floor approved for cover. Re-inspection at the main street entry vestibule and lobby okayed. Noted the need to remove valves in sensing lines at the FP and JP.
|
INSP-Sprinkler Rough-in | 6/12/2014 | 6/13/2014 | 6/13/2014 | A | FAIL |
Forrest France
|
|
|
Inspection for overhead cover at the 1st floor main street side entry lobby and vestibule failed due to overspaced pendent heads and missing hanger at the main.
|
INSP-Sprinkler Rough-in | 6/2/2014 | 6/2/2014 | 6/2/2014 | A | PART |
Forrest France
|
|
|
Regarding conditions for ceiling pockets per NFPA 13 8.6.7.2 (1-6).
|
INSP-Sprinkler Rough-in | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PART |
Forrest France
|
|
|
Basement level elevator lobby grid ceiling as marked and dated on approved plans okayed for cover.
|
INSP-Sprinkler Rough-in | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Forrest France
|
|
|
1st floor mens and womens restroom entry vestibules approved for cover as marked and dated on stamped plan set.
|
INSP-Sprinkler Rough-in | 5/5/2014 | 5/5/2014 | 5/5/2014 | A | PART |
Forrest France
|
|
|
Install at plan mod two sheets FP0.1- FP1 passed rough-in.
|
INSP-Sprinkler Rough-in | 4/23/2014 | 4/24/2014 | 4/24/2014 | A | PART |
Forrest France
|
|
|
Inspection for cover at the 1st floor west entry and corridor sheetrock ceiling areas- refer to clouded notes with today's date on stamped plans.
|
INSP-Sprinkler Rough-in | 4/22/2014 | 4/22/2014 | 4/22/2014 | A | PART |
Forrest France
|
|
|
OH rough-in as marked on stamped plans at the lobby and reception areas okayed.
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/18/2014 | 4/18/2014 | A | PART |
Forrest France
|
|
|
Okay to cover overhead work at the 5th floor mens and womens restrooms and adjacent vestibules- Refer to dated annotations on stamped plan set.
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/17/2014 | 4/17/2014 | P | CANC |
Forrest France
|
|
|
Terry Nelson Phone #: ###-#### - - terry called in and canceled and reschuled for tomorrow morning /// 4-17-14 ps
|
INSP-Sprinkler Rough-in | 3/26/2014 | 3/26/2014 | 3/26/2014 | A | PART |
Forrest France
|
|
|
1st floor hard lid areas as marked on plans okay for cover-
|
INSP-Sprinkler Rough-in | 3/24/2014 | 3/25/2014 | 3/25/2014 | A | PART |
Forrest France
|
|
|
Okay to cover overhead work at the first floor sheetrock ceilings "oasis" area and east elevator lobby as clouded and dated on approved plans. Discussed project schedule and hydro testing.
|
INSP-Sprinkler Rough-in | 3/20/2014 | 3/20/2014 | 3/20/2014 | P | PART |
Forrest France
|
|
|
Verified coverage per plan mod #2 sheet FP0.1 - upright protection at the crawl space below 1st floor. 1st floor reception, west elevator lobby, mens and womens restrooms, and mail room ceilings approved for cover, marked on plans with todays date.
|
INSP-Sprinkler Rough-in | 12/2/2013 | 12/3/2013 | 12/3/2013 | A | NR |
Forrest France
|
|
|
Project not in condition to complete a satisfactory pump acceptance test at this time.
|
INSP-Sprinkler Rough-in/Hydro | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PART |
Forrest France
|
|
|
Completed hydrostatic test of the new suction piping at the fire pump.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2013 | 11/27/2013 | 11/27/2013 | P | PEND |
Forrest France
|
|
|
This is for a fire pump test please call Lonnie for time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham *Refer to NFPA 20 regarding items to be completed prior to pump acceptance testing including pump, valve and controler monitoring (run, power loss, phase reversal, tampers, etc.), complete a hydrostatic test for both suction and discharge piping, provide test equipment to verify volts, amperes and pump speed during operation, ensure wiring has been completed and checked by the electrical contractor previous to initial startup. Provide certified pump curve for field comparison.
|
INSP-Sprinkler Rough-in | 11/20/2013 | 11/21/2013 | 11/21/2013 | A | PART |
Forrest France
|
|
|
UG fire supply line and yard PIV at Main street okayed for cover.
|
INSP-Sprinkler Rough-in | 10/31/2013 | 10/31/2013 | 11/1/2013 | P | PART |
Forrest France
|
|
|
Rough-in for the 7th floor completed- okay to cover areas with sheetrock ceilings at the RR's and hallway. Missing coverage at one closet per plan- ref. dated annotation. Also noted lacking coverage (existing conditions) at the elevator machine room, penthouse, and some areas between floor levels of the basement, 1st and 2nd.
|
INSP-Sprinkler Rough-in | 6/9/2014 | 6/9/2014 | | P | |
Forrest France
|
|
|
Terry at phone #: ###-####
|