INSP-Final Inspection | 9/22/2014 | 9/23/2014 | 9/23/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/23/2014 | 7/23/2014 | 7/23/2014 | A | PART |
Forrest France
|
|
|
Previous correction items verified for completion.
|
INSP-Final Inspection | 6/30/2014 | 6/30/2014 | 7/1/2014 | P | PART |
Forrest France
|
|
|
Noted items on walkthrough of the 2nd, 3rd and 4th floor apartment units include taped head/missing escutcheon at unit 206, need to provide intermediate temp head at unit 312 adjacent to HVAC diffuser, flow switches at the 3rd and 4th floor are malfunctional, missing outside waterflow bell.
|
INSP-Sprinkler Rough-in | 3/20/2014 | 3/20/2014 | 3/20/2014 | P | PART |
Forrest France
|
|
|
Okay to cover overhead work at the 3rd floor mens and womens restrooms.
|
INSP-Sprinkler Rough-in | 2/26/2014 | 2/27/2014 | 2/27/2014 | A | PART |
Forrest France
|
|
|
As noted on plans
|
INSP-Sprinkler Rough-in | 2/25/2014 | 2/26/2014 | 2/26/2014 | A | PART |
Troy Cobbley
|
|
|
One small soffit is ok to cover, see marked plans, the other areas request for inspection need sheet rock removed so I can see the piping.
|
INSP-Sprinkler Rough-in | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work at the second floor units- kitchens and bathrooms.
|
INSP-Sprinkler Rough-in/Hydro | 2/4/2014 | 2/5/2014 | 2/5/2014 | A | PART |
Forrest France
|
|
|
Completed overhead hydrostatic test of the wet system 2nd floor west wing. Also completed cover inspection of the corridor drop ceiling, unit kitchens and bathroom ceilings. Noted exposed combustible construction above the ceiling lids to be covered with sheetrock.
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2014 | 1/14/2014 | 1/14/2014 | A | PART |
Forrest France
|
|
|
Completed hydrostatic testing for the 3rd floor west wing units and corridor.
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2013 | 12/11/2013 | 12/11/2013 | P | PASS |
Forrest France
|
|
|
Hydro 4th floor residential area passed.
|
INSP-Sprinkler Rough-in | 12/4/2013 | 12/4/2013 | 12/4/2013 | P | PART |
Forrest France
|
|
|
Overhead work at the 4th floor corridor including the remainder of hard lid soffits are okay for cover. One pendent head to be adjusted as discussed.
|
INSP-Sprinkler Rough-in | 11/20/2013 | 11/20/2013 | 11/20/2013 | P | PART |
Forrest France
|
|
|
Verified soffits at the 4th floor guest rooms adjacent to outside windows are filled with non-combustible insulation.
|
INSP-Sprinkler Rough-in | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed for work at the 2nd floor guest rooms- okayed for ceiling cover.
|
INSP-Sprinkler Rough-in | 10/31/2013 | 10/31/2013 | 11/1/2013 | P | PART |
Forrest France
|
|
|
Rough-in inspection for the 3rd floor unit rooms only- Identified concealed combustible spaces at some areas in need of coverage or meet allowable conditions per NFPA 13. Clarify if space between ceiling and deck above the kitchens will be sheetrocked. Plan modification to include deleted pendents at the end of lines in some units. Branchlines and head spacing okayed.
|
INSP-Sprinkler Rough-in | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | PART |
Craig D. Hanson
|
|
|
this was for 4th floor cover of branchlines into rooms. Main and connection will be installed below hard lid and will be inspected later. No hydro of pipe being covered, installer responsible for any leaks in covered pipe.concealed sofit on each side of 4th floor needs insulation or to be spinkled.
|