INSP-Final Inspection | 1/30/2014 | 2/3/2014 | 2/3/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/17/2014 | 1/21/2014 | 1/21/2014 | A | PART |
Troy Cobbley
|
|
|
This inspection is for temporary occupancy permit request for GC. All FA work completed except for front door mag release. There is no hardware on front door. ok for temp permit, per Scott Aranello on 1/16/14.
-Submitted by Scott Ramella ###-#### cell Phone #: ###-#### >> Inspection requested via web by Scott Ramella
|
INSP-Final Inspection | 1/13/2014 | 1/13/2014 | 1/13/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide correct netcon for the transmitter, provide signage on door, repair outside alarm bell, repair the smoke dampers, provide map at the FACP, provide/finish installing the mag lock system...ect. See city approved plans for complete list.
|