Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR14-00069
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 4032 S COUNCIL SPRING RD
Project NameThe Terraces - Bldg J
Customer NumberUDG ONLY
ePlanReviewYes
Description
The fire sprinkler scope of work consists of 6”x44± C-900 underground piping with a yard PIV.
Plan Mod #1 - 11/25/2014
Revised underground layout.
To construct a new 11,850 square foot, one story, wood framed skilled nursing facility and related site improvements. This nursing home will contain 16 sleeping units with individual restrooms, as well as, a kitchen, dining and hearth room social area. This building will also contain a hair salon, laundry, storage and mechanical areas. This building is divided into two smoke compartments by a one-hour smoke barrier wall. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/17/20159/21/20159/21/2015PPASS
DetailsThomas Walsh
Duplicate request - Final inspection of FS U/G supply - PASSED
Tamper valve interface with fire alarm system OK
INSP-Sprinkler Rough-in9/17/20159/21/20159/21/2015PPASS
DetailsThomas Walsh
Duplicate request - Final inspection of FS U/G supply - PASSED
Tamper valve interface with fire alarm system OK
INSP-Sprinkler Rough-in/Hydro9/17/20159/21/20159/21/2015PPASS
DetailsThomas Walsh
Final inspection of FS U/G supply - PASSED
Tamper valve interface with fire alarm system OK
INSP-Final Inspection5/29/20156/1/20156/1/2015PCANC
DetailsThomas Walsh
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
INSP-Sprinkler Rough-in/Hydro5/29/20156/1/20155/29/2015PCANC
DetailsThomas Walsh
Please call Leroy 30 mins prioor Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Sprinkler Rough-in/Hydro5/18/20155/19/20155/19/2015APASS
DetailsThomas Walsh
Hydrotest of FSUG system - from city check valve to BFP. No loss of pressure noted for 2 hours. System has been flushed at previous inspection.
INSP-Sprinkler Rough-in/Hydro5/18/20155/19/20155/18/2015PCANC
DetailsTroy Cobbley
Rough in Hydro UG
Please call Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Conference4/24/20154/27/20154/27/2015ADONE
DetailsKatie Marron
TOB Bldg. J - Underground. Phone conference complete. Verified that underground fire line must be able to hold 200 psig. General contractor installed up to PIV and only holds 130 psig currently.
INSP-Supply line flush2/13/20152/13/20152/13/2015PPART
DetailsForrest France
UG fire supply line flush completed
INSP-Sprinkler Rough-in7/14/20147/14/20147/14/2014PPASS
DetailsTroy Cobbley
Underground supply piping is ok to cover.