INSP-Final Inspection | 4/21/2014 | 4/22/2014 | 4/22/2014 | P | PASS |
Forrest France
|
|
|
Completed remainder of acceptance test including heat detectors, verified documents box, map at the panel updated, recieved record of completion forms. Fire alarm permit finaled.
|
INSP-Final Inspection | 4/18/2014 | 4/21/2014 | 4/21/2014 | P | PART |
Forrest France
|
|
|
Verified additional smoke detection per noted revisions. Okay to final when documents enclosure is provided. Will accept as-builts at final.
|
INSP-Final Inspection | 4/15/2014 | 4/16/2014 | 4/16/2014 | P | PART |
Forrest France
|
|
|
Final pending the addition of two smoke detectors to complete full area coverage, need to post documents cabinet per NFPA 72, provide as-builts for modifications. Heat detectors not tested at this time. Items tested today include FACP, RA, occupant notification, manual pull stations, smoke detection, and offsite monitoring,
|
INSP-Conference | 4/15/2014 | 4/15/2014 | 4/15/2014 | P | DONE |
Forrest France
|
|
|
Regarding requirements per NFPA 72- 2013
|
INSP-Alarm Testing | 3/5/2014 | 3/11/2014 | 3/7/2014 | P | CANC |
Forrest France
|
|
|
At 2:00 P.M. would be best. Phone #: ###-#### >> Inspection requested via web by Duane O'Reilly Inspection cancelled from web by: Duane O'Reilly
|