INSP-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit final approved.
|
INSP-Sprinkler Rough-in | 10/20/2014 | 10/20/2014 | 10/20/2014 | P | PART |
Forrest France
|
|
|
Regarding overhead permit work FIR14-00261
|
INSP-Sprinkler Rough-in/Hydro | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line passed hydrostatic testing.
|
INSP-Supply line flush | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Final Inspection | 8/6/2014 | 8/7/2014 | 8/6/2014 | A | CANC |
Forrest France
|
|
|
Jeremiah is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | CANC |
Forrest France
|
|
|
Jeremiah is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | CANC |
Forrest France
|
|
|
This is an ug hydro. Jeremiah is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | PART |
Forrest France
|
|
|
Remainder of UG fire supply line to the point of connection at the property line is approved for bury.
|
INSP-Sprinkler Rough-in | 2/21/2014 | 2/21/2014 | 2/21/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line ductile riser and stub to a point 9' beyond the stem wall approved for bury.
|