INSP-Final Inspection | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Forrest France
|
|
|
Correction items verified for completion. Fire alarm inspection and functional testing passed. Permit finaled.
|
INSP-Final Inspection | 5/30/2014 | 5/30/2014 | 5/30/2014 | P | FAIL |
Forrest France
|
|
|
C/N items include; adjust spacing and cd settings at several notification appliances, relocate SD's at the nac and facp away from diffusers, installation to match plans. Noted MP's have been relocated and review red-line item finished.
|
INSP-Final Inspection | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | FAIL |
Troy Cobbley
|
|
|
Canceled by Brian as I pulled up. Per Brian two more pull stations are going to be added. I noted that the new pull stations currently installed too high. Also the smoke detector shown as existing located over the FACP is not installed and will unless documentation is provided showing is does not need to be installed. No actual testing was performed.
|