Information based on query as of Monday, July 15, 2024.
Permit Information
Permit NumberFIR14-00191
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1011 S LA POINTE ST
Project NameBoise Heights
Customer NumberUDG ONLY
ePlanReviewYes
Description
8" C-900 underground water supply pipe and fittings from property line to within 10' from outside wall.

Boise Heights - Grading/Dranage - Permit to excavate, grade import and compact site earth materials in preparation for a 5 floor multi-family structure. This permit includes installation of underground site utilities, drainage features and structural fill. **Special inspections are required for structural fill.** NO CONSTRUCTION IS ALLOWED UNDER THIS PERMIT. Reference DRH13-00204, CUP13-00040 for planning approvals. //leg
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/26/20158/27/20158/27/2015APASS
DetailsThomas Walsh
Final inspection and signoff for this permit.
INSP-Sprinkler Rough-in/Hydro6/23/20156/23/20156/23/2015PPASS
DetailsThomas Walsh
FS U/G supply OK to final, per Scott Arellano's email, dated 6/23/15. Hydrotest and flush of U/G supply witnessed by this office, but not documented in permit file.
INSP-Final Inspection6/11/20156/11/20156/11/2015PPEND
DetailsThomas Walsh
Inspection request to final FS U/G installation, although the hydrotest and flushing could not be confirmed by reviewing completed inspections recorded in permit activities file. I called Forest to confirm that these inspections were witnessed by him, which is contended by the fire sprinkler contractor. Will advise the contractor and GC accordingly.
INSP-Supply line flush9/26/20149/29/20149/29/2014ANR
DetailsForrest France
Nate is the contact. Thanks Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush9/25/20149/26/20149/26/2014ANR
DetailsForrest France
Pending water supply to complete flushing.
INSP-Supply line flush9/24/20149/25/20149/26/2014ACANC
DetailsCraig D. Hanson
INSP-Sprinkler Rough-in7/25/20147/28/20147/28/2014APART
DetailsCraig D. Hanson
Underground, west side of building, OK to cover
INSP-Sprinkler Rough-in5/12/20145/12/20145/12/2014APART
DetailsForrest France
UG cover okayed
INSP-Sprinkler Rough-in4/9/20144/9/20144/9/2014PPART
DetailsForrest France
UG fire supply line including the ductile riser and stub out to a point 10' beyond the riser okayed for bury.
INSP-Sprinkler Rough-in4/8/20144/9/20144/9/2014APART
DetailsForrest France
Verified ductile riser, thrust block and approved plan set- remainder of supply line could not be inspected due to bury already complete- need to uncover piping to finish inspection.
INSP-Sprinkler Rough-in4/7/20144/8/20144/8/2014PDEFR
DetailsForrest France
This is an ug to cover. Bryan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus