INSP-Final Inspection | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Forrest France
|
|
|
Final walkthrough completed. Need to adjust one pendent head at the dining area, replace missing escutcheon at the basement level rec room. Flow testing passed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PART |
Forrest France
|
|
|
Previous correction items verified for completion including the riser, coverage at the fireplace, and tenting. Plan modification approval pending for changed pipe sizes, relocated branchlines, heads, etc.- okayed for cover conditional upon plan revision.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed acceptable. Discussed conditions per NFPA 13D 8.6.5.1.
|
INSP-Sprinkler Rough-in/Hydro | 7/3/2014 | 7/7/2014 | 7/7/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Robert
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2014 | 7/7/2014 | 7/7/2014 | A | FAIL |
Troy Cobbley
|
|
|
Resubmitt plans showing all of the additional fittings and routing changes. Provide steel riser. Provide pipe sizing as per the plans. Provide sprinkler coverage above the fire place. Provide tenting as discussed. Provide enclosure for piping above garage as per approved plans. Do not cover piping.
|
INSP-Supply line flush | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/17/2014 | 4/17/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line and stub-in approved for cover.
|