INSP-Final Inspection | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 6/26/2014 | 6/27/2014 | 6/27/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed in the Lab area. Piping can be covered.
|
INSP-Sprinkler Rough-in | 6/12/2014 | 6/13/2014 | 6/13/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms where the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 5/9/2014 | 5/12/2014 | 5/12/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the phase/location where sprinkler piping is ok to cover marked with todays dat.
|
INSP-Sprinkler Rough-in | 5/8/2014 | 5/9/2014 | 5/9/2014 | P | CANC |
Troy Cobbley
|
|
|
partial rough in Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|
INSP-Sprinkler Rough-in | 5/8/2014 | 5/9/2014 | 5/8/2014 | A | CANC |
Troy Cobbley
|
|
|
Partial Rough in Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|