INSP-Final Inspection | 8/7/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/5/2014 | 8/5/2014 | 8/5/2014 | P | PART |
Forrest France
|
|
|
Items needed prior to final include; provide intermediate temp sprinkler at the main entry area womens restroom adjacent to the HVAC diffuser, remove two travel clips at the south classroom, existing system is overdue annual inspection. Missing escutcheons installed while on site. Remainder of final walkthrough passed.
|
INSP-Sprinkler Rough-in | 7/25/2014 | 7/28/2014 | 7/28/2014 | A | PASS |
Craig D. Hanson
|
|
|
all areas have been inspected and passed for rough in cover. Hydro done and pass.
|
INSP-Sprinkler Rough-in | 7/23/2014 | 7/23/2014 | 7/23/2014 | A | PART |
Forrest France
|
|
|
Grid ceiling areas as marked on plans okayed for cover.
|
INSP-Sprinkler Rough-in | 7/22/2014 | 7/22/2014 | 7/22/2014 | P | PART |
Forrest France
|
|
|
Inspection for cover at grid ceilings completed to date- Items noted include; insufficient coverage the janitors and IT rooms due to OTS ceiling configuration, need to add upright coverage at a concealed space overbuild above classroom 119. Commons classroom, corridor grid, and main tie-in above the 5th grade classroom are not yet finished. Verified added uprights along the north and south main corridor rated walls. Discussed hydrostatic testing per review notes and NFPA guidelines. Need record drawings for field modifications. Remainder of classrooms approved for ceiling cover as noted on plans.
|
INSP-Sprinkler Rough-in | 7/8/2014 | 7/9/2014 | 7/10/2014 | A | PART |
Forrest France
|
|
|
Okay to cover upright protection at the south end of the central skylight past the fire wall. *Note- existing upright sprinklers at the west corridor and adjacent classrooms in need of adjustment to maintain deflectors parallel to the ceiling in accordance with NFPA 13 2013 sec. 8.1(3) and 8.6.4.2.1.
|
INSP-Sprinkler Rough-in | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | PART |
Forrest France
|
|
|
For overhead cover at grid ceilings
|
INSP-Sprinkler Rough-in | 7/3/2014 | 7/7/2014 | 7/7/2014 | A | PART |
Forrest France
|
|
|
Inspection for overhead cover at an office, two restrooms, vestibule, and seven classrooms as marked and dated on approved plans okayed for drop ceiling cover. Need to add upright protection at one pocket above the NW corner of the 5th grade classroom, provide intermediate temp head at the office due to proximity to an HVAC diffuser.
|
INSP-Sprinkler Rough-in | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PART |
Forrest France
|
|
|
Sheetrock soffits as dated on plans okayed for cover. Modifications at the atrium area to show on plan mod., need to add one head below ductwork at the concealed space per discussion.
|
INSP-Sprinkler Rough-in | 6/24/2014 | 6/24/2014 | 6/24/2014 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PART |
Forrest France
|
|
|
Okay to cover overhead work at sheetrock ceilings in selected areas as marked/dated on approved plans. Noted two locations at corridor vestibules in need of spacing adjustments.
|