Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR14-00285
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 7009 W FRANKLIN RD
Project NameBishop Kelly East Wing Additio
Customer Number 
ePlanReviewYes
Description
Shilo will add a new riser after the existing backflow and run new 3" and 2½" main to the new East Wing addition. Shilo will then install the main line, branch lines, and armovers with new pendent sprinklers.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/5/20148/6/20148/6/2014APASS
DetailsForrest France
Fire sprinkler permit work passed final walkthrough.
INSP-Final Inspection8/4/20148/5/20148/5/2014AFAIL
DetailsTroy Cobbley
Could not complete inspection due to fire alarm problems
INSP-Final Inspection8/1/20148/4/20148/4/2014ACANC
DetailsTroy Cobbley
Please call 1/2 hr prior to inspecion. Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection7/31/20148/1/20148/1/2014ACANC
DetailsTroy Cobbley
We were told there is a final and the alarm called in already. Werent sure
if its am or pm. Please call Mark 1/2 hr prior to inspection. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro7/24/20147/25/20147/25/2014APASS
DetailsTroy Cobbley
The overhead hydro test passed. Rough-in inspection for overhead piping passed. Piping can be covered.
INSP-Sprinkler Rough-in6/17/20146/17/20146/17/2014PPART
DetailsForrest France
Verified seismic bracing at the mains and terminus of branchlines- (5 classrooms, 12 branchlines).
INSP-Sprinkler Rough-in6/5/20146/6/20146/6/2014APART
DetailsTroy Cobbley
Inspection was for just the branchlines and related components since the sprinkler drops are not installed yet. Branchline restraints and earth quake bracing is missing. Also wood sheating has been installed around the exterior walls of the building. Per conversation with the building contractor this wood will be covered with sheet rock. If sheet rock is not installed then upright sprinkler protection will be required as well as resubmittals.