INSP-Final Inspection | 8/5/2014 | 8/6/2014 | 8/6/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final walkthrough.
|
INSP-Final Inspection | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | FAIL |
Troy Cobbley
|
|
|
Could not complete inspection due to fire alarm problems
|
INSP-Final Inspection | 8/1/2014 | 8/4/2014 | 8/4/2014 | A | CANC |
Troy Cobbley
|
|
|
Please call 1/2 hr prior to inspecion. Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | CANC |
Troy Cobbley
|
|
|
We were told there is a final and the alarm called in already. Werent sure if its am or pm. Please call Mark 1/2 hr prior to inspection. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed. Rough-in inspection for overhead piping passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 6/17/2014 | 6/17/2014 | 6/17/2014 | P | PART |
Forrest France
|
|
|
Verified seismic bracing at the mains and terminus of branchlines- (5 classrooms, 12 branchlines).
|
INSP-Sprinkler Rough-in | 6/5/2014 | 6/6/2014 | 6/6/2014 | A | PART |
Troy Cobbley
|
|
|
Inspection was for just the branchlines and related components since the sprinkler drops are not installed yet. Branchline restraints and earth quake bracing is missing. Also wood sheating has been installed around the exterior walls of the building. Per conversation with the building contractor this wood will be covered with sheet rock. If sheet rock is not installed then upright sprinkler protection will be required as well as resubmittals.
|