INSP-Final Inspection | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection of A, B & C wings - wet pipe systems.ALL PASSED. Fire alarm system interface also finaled this day.
|
INSP-Final Inspection | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection of Bldg. D and commons area. Lobby sprinkler at 2nd floor level has protective cap still on. Will need to get a lift to access. Will reschedule final signoff, otherwise rest of system inspected OK
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | CANC |
Thomas Walsh
|
|
|
Fire sprinkler final inspections will be conducted following completion of fire alarm system testing.
|
INSP-Final Inspection | 6/5/2015 | 6/8/2015 | 6/8/2015 | P | PART |
Thomas Walsh
|
|
|
Inspection of fire alarm interface, including water flows, tamper supervisory devices, pump activations, etc., also exterior bell activation. All W/F tested OK (within 90 seconds - mostly around 30-40 seconds). All addresses appeared OK
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest - 200 psi @ 2hours - Passed
|
INSP-Sprinkler Rough-in | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | PART |
Katie Marron
|
|
|
Small area with two heads in Basement of A/B/C near elevator ok to cover.
|
INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/3/2015 | P | PART |
Forrest France
|
|
|
Completed overhead inspection for cover at the 2nd floor building areas A, B, and C for sheetrock lids at the corridor, service use rooms, and common areas as marked and dated on approved plans. Items noted include; one head to be relocated, missing hanger at the 2" main in housekeeping, relocate capped drop, SW heads at area A in three locations are not yet installed. Discussed max head spacing at the corridors, locations per plan where standard pendent heads are to be provided, proximity of light fixture junction boxes to sprinklers.
|
INSP-Sprinkler Rough-in | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | PART |
Forrest France
|
|
|
Inspection for 1st floor building C soffits completed- okayed for cover.
|
INSP-Sprinkler Rough-in | 12/2/2014 | 12/3/2014 | 12/9/2014 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 11/17/2014 | 11/18/2014 | 11/19/2014 | A | PART |
Forrest France
|
|
|
Bldg B 4th Floor RTC Pls call Roy 30 mins prior Phone #: ###-#### Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 11/5/2014 | 11/5/2014 | 11/6/2014 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PART |
Forrest France
|
|
|
Completed rough-in for install to date at the first floor wet system building areas A, B, and C. Refer to dated annotations on plan sheet for locations and items noted including; missing coverage at HVAC closet unit B105, relocate head at unit B106 kitchen, revise hangers at end of pendent armovers various locations, as-builts needed for field modifications such as relocated 2" main, moved SW, deleted SW coverage at area A, branchline re-routes, etc., corridor main is not yet installed, 3 groups of rooms as clouded NR.
|
INSP-Sprinkler Rough-in | 10/28/2014 | 10/29/2014 | 10/30/2014 | P | PART |
Forrest France
|
|
|
Inspection for the wet system building A 2nd floor completed for units A201 and A202. Insufficient tenting at two locations revised while on site, noted field mods at unit A202- DSW head feed repiped.
|
INSP-Sprinkler Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 | P | PART |
Forrest France
|
|
|
Rough-in at building C 2nd floor completed. Items noted include; overspaced SW head at unit C206, coverage at mechanical, trash and storage rooms overspaced- install per design, plan modification necessary for field changes to 2" main and branchline layout, housekeeping room and 2" main in the corridor not yet installed. Previous C/N items done.
|
INSP-Sprinkler Rough-in | 10/14/2014 | 10/15/2014 | 10/16/2014 | P | PART |
Forrest France
|
|
|
Rough-in at 2nd floor building B completed. Items noted include; min spacing at unit C208, unfinished 2" main to mechanical room, obstructed sprinkler coverage at unit C202, fire blocking incompleted at some locations. Housekeeping, trash, mechanical rooms not yet finished.
|
INSP-Sprinkler Rough-in | 10/10/2014 | 10/13/2014 | 10/13/2014 | A | CANC |
Troy Cobbley
|
|
|
Roy was not quite ready yet so he is going to reschedule. Rough in for 2nd Floor Wet Ceiling Bldg C Please call Roy 30 mins prior Phone #: ###-#### Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 10/7/2014 | 10/8/2014 | 10/8/2014 | A | PART |
Forrest France
|
|
|
Inspection for joist space fire stopping at building B 3rd floor completed. Rough-in at the 4th floor area B 2" main also finished including branch line tie-ins to apartments units.
|
INSP-Sprinkler Rough-in | 10/3/2014 | 10/6/2014 | 10/6/2014 | P | PART |
Forrest France
|
|
|
Completed inspection for cover at building area B 3rd floor. Items noted include; one restroom missing a sprinkler head per plan-(install or remove from plan per NFPA exceptions), missing coverage at a housekeeping closet, areas not completed at this time include 2"main at corridor, elevator lobby, mechanical, data, and trash rooms. Adjustments to coverage at three locations completed while on site. Discussed fire stop at joist channels <160ft3.
|
INSP-Sprinkler Rough-in | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | PART |
Forrest France
|
|
|
Rough-in inspection for portions of building B 4th floor completed to date- Items noted include; three overspaced CC2 heads, relocate one CC2 away from truss web, SW heads and supply piping are not yet installed, 2" CPVC main at the corridor and extending into one unit is not installed, two additional branchlines with CC2 heads have been installed due to draft stops and are not included on plans. The trash room, elevator lobby, data, and housekeeping areas are not piped at this time. Refer to plans for annotations.
|
INSP-Sprinkler Rough-in | 10/1/2014 | 10/2/2014 | 10/3/2014 | P | PART |
Forrest France
|
|
|
Third floor area C wet system piping okayed for ceiling cover. Noted corrections completed.
|
INSP-Sprinkler Rough-in | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | CANC |
Forrest France
|
|
|
Please call Roy 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 | P | PART |
Forrest France
|
|
|
Completed rough-in for the remainder of 3rd floor area C. Items noted include; SW heads at six locations are not installed or piped, repair damaged hanger, plan modification will be necessary for changes to pipe routing and type at the trash, storage, elev. lobby, houskeeping, and adjacent hallway areas, tenting at some locations adjusted while on site. Ref. plans for annotations.
|
INSP-Sprinkler Rough-in | 9/18/2014 | 9/19/2014 | 9/19/2014 | A | PART |
Forrest France
|
|
|
Verified corrections and adjustments for the wet system as noted 3rd floor north end building area C. Okayed for cover at four units- * need to verify insulation fill at two locations, discussed documentation for changes to install vs. approved plan.
|
INSP-Sprinkler Rough-in | 9/18/2014 | 9/18/2014 | 9/18/2014 | A | FAIL |
Forrest France
|
|
|
Items noted for rough-in inspection at the 3rd floor building C north end (four units and corridor) as marked/dated on stamped plans include; provide cap at the end of main per plan to meet NFPA 13 8.16.3, four additional 1 1/4 90's and piping have been added to calc area #2, maintain clearance from ceiling fans to pendent heads, overspaced coverage at one location due to a corridor wall not shown on drawings, not all light fixtures are recessed as indicated on plans, need to verify insulation or sprinkler coverage at combustible concealed spaces (chases) prior to cover, missing hanger at 1 1/4 branchline in the hall, min. spacing between heads is exceeded in the kitchen area at one unit, field modification to sprinklers and piping does not match plans in one unit (4 heads off 1" feed), missing head per plan at one ADA bathroom - provide coverage or delete and include change on plan mod, tenting at several areas insufficient and adjusted while on site. Also noted significant changes to field installation at the mechanical, data, corridor and trash rooms compared to the design and approved plan set.
|
INSP-Sprinkler Rough-in | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PART |
Forrest France
|
|
|
Overbooked AM inspection schedule- Inspection to be continued in the afternoon per on site discussion.
|
INSP-Sprinkler Rough-in | 9/15/2014 | 9/16/2014 | 9/16/2014 | P | CANC |
Forrest France
|
|
|
Please call Tyler 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 9/15/2014 | 9/16/2014 | 9/15/2014 | A | CANC |
Forrest France
|
|
|
Please call Scott 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 12/29/2014 | 12/30/2014 | | P | |
Forrest France
|
|
|
Inspection for 1st floor soffits area a and b. Contact is Raul ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Carter II
|