INSP-Final Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspections completed.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/18/2015 | 8/18/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrostatic test of FDC supply line for the 11th street supply line (200 psi @ 2hours) -PASSED.NOTE: Permit for FSUG is FIR13-00167
|
INSP-Final Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PART |
Thomas Walsh
|
|
|
Reinspection of fire sprinkler systems for Helix and above ground FP systems, including inspection of punchlist items from last inspection. All punchlist items adeqautely addressed. Main WF electric bell to be installed outside of main FACP control room. Also tested main PIVs (9th and 11th streets). Both were not working correctly and will be retested after repaired/replaced.
|
INSP-Final Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection for Helix structure and above ground parking garage, and all rooms located above the parking garage. NOTE: Some DP heads in the parking garage not installed yet. Some other minor punchlist items remain that will require re-inspection. Also, exterior alarm bell required to be installed near exterior of the command center, and be tied into all waterflow alarms to indicate a water flow from any system within the structure.
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2015 | 8/3/2015 | 8/3/2015 | P | PASS |
Thomas Walsh
|
|
|
Fire pump commissioning test with MFG's rep. Tested 0 flow. 100% and 150% with generator and both supplies open. All tested OK. Pump test report to e emailed to Tim Frost.
|
INSP-Conference | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | DONE |
Thomas Walsh
|
|
|
Meeting with elect. contractor (Tony) to discuss clearance around hose valve from emergency lighting unit.
|
INSP-Alarm Testing | 7/12/2015 | 7/12/2015 | 7/12/2015 | P | PART |
Thomas Walsh
|
|
|
Test of dry pipe valves for 2nd and 3rd floor Helix structure, which includes ramp and some areas surrounding the ramp. Trip test of DP valves, including trip tests, low-air, waterflow and tampers. All tested OK NOTE: Other systems protecting the Helix (floors 1 thru 6) have now been tested and passed. Kitchen and 2nd floor lobby on another permit.
|
INSP-Final Inspection | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PASS |
Thomas Walsh
|
|
|
Trip test of the dry-pipe valves for the Helix at levels 2 and 3. All tested OK
|
INSP-Final Inspection | 7/8/2015 | 7/9/2015 | 7/9/2015 | P | PART |
Thomas Walsh
|
|
|
Inspection of Helix dry-pipe systems for fire alarm interface, including water flows, tampers, low-air signals and including trip tests - all floors except levels 2 and 3. All tested OK and within 60 seconds of flow test. NOTE: 6th floor wet system not programed into alarm system - will retest.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2015 | 6/19/2015 | 6/19/2015 | P | PASS |
Thomas Walsh
|
|
|
24 hour air test of dry pipe valves for six (6) systems, including 2nd floor Helix, 3rd floor Helix, 3rd floor parking garage, 4th floor Helix, 4th floor parking garage, and 5th floor Helix - all system air tests held pressure. PASSED
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2015 | 6/18/2015 | 6/18/2015 | P | PART |
Thomas Walsh
|
|
|
This is a 24 hour air test of six (6) dry pipe valves, as floows; 2nd floor helix, 3rd floor helix, 3rd floor P/G, 4th floor helix, 4th floor P/G and 5th floor helix. Will retest air pressures at 1:30pm on 6/19.
|
INSP-Sprinkler Rough-in/Hydro | 6/10/2015 | 6/10/2015 | 6/10/2015 | P | CANC |
Thomas Walsh
|
|
|
Wrong permit # called in for this inspection. Will add inspection to the correct permit # FIR13-00275
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2015 | 5/16/2015 | 5/16/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest of helix dry systems - levels 2, 4 and 5, and 5th floor wet-pipe system
|
INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 | A | PART |
Forrest France
|
|
|
Inspection for cover at the 2nd and 3rd floor service elevator lobby drop ceilings and 2nd level 3" dry main at west side heilix. Discussed project schedule and work completed to date.
|