INSP-Final Inspection | 10/13/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Craig D. Hanson
|
|
|
|
INSP-Final Inspection | 10/7/2014 | 10/8/2014 | 10/8/2014 | P | PART |
Forrest France
|
|
|
Final pending outside bell, flow test per contractor.
|
INSP-Sprinkler Rough-in | 7/10/2014 | 7/11/2014 | 7/11/2014 | A | PART |
Forrest France
|
|
|
Previous correction items verified for completion. Rough-in okay for cover.
|
INSP-Sprinkler Rough-in | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | FAIL |
Forrest France
|
|
|
A newly added closet has blocked fire sprinkler coverage adjacent to the nook and kitchen areas, tenting is not adequate at two locations including a bedroom and the riser piece to the great room. Previous correction items are finished. Cover is not approved at this time.
|
INSP-Supply line flush | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed acceptable.
|
INSP-Sprinkler Rough-in | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed. Need to install missing coverage at a closet and provide head per plan review comments at the fireplace.
|
INSP-Sprinkler Rough-in | 6/30/2014 | 6/30/2014 | 6/30/2014 | P | CANC |
Forrest France
|
|
|
Mike M is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|