INSP-Final Inspection | 12/19/2014 | 12/22/2014 | 12/22/2014 | P | PASS |
Forrest France
|
|
|
Correction items and retest of the forward flow completed and passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | NR |
Forrest France
|
|
|
Items needed prior to final include finish pack at the riser (signs, calc stickers, state tags), certify DCVA. Forward flow did not meet design specs.
|
INSP-Final Inspection | 12/16/2014 | 12/17/2014 | 12/18/2014 | P | CANC |
Forrest France
|
|
|
Overbooked- To be rescheduled as discussed
|
INSP-Supply line flush | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed.
|
INSP-Sprinkler Rough-in | 11/3/2014 | 11/3/2014 | 11/3/2014 | P | PART |
Forrest France
|
|
|
OH rough-in inspection at mains and branchlines completed in conjunction with hydrostatic testing 10/8.
|
INSP-Sprinkler Rough-in/Hydro | 10/7/2014 | 10/8/2014 | 10/8/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line and new overhead system both passed hydrostatic testing.
|
INSP-Sprinkler Rough-in | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | PASS |
Craig D. Hanson
|
|
|
underground rough in pass. Ok to cover.
|