Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR14-00529
StatusFinaled
Name AFP SYSTEMS INC
Site Address 5500 S FEDERAL WAY
Project NameOre Pack Boise Warehouse
Customer Number 
ePlanReviewYes
Description
[Ore Pac]
The fire sprinkler scope of work consists of protecting an existing building and new building with four dry systems. A new fire pump (1500 Gpm @ 90 Psi) will be installed. ELO 231 sprinklers are being utilized. A new fire pump room will be built in the new portion of the building. The building has 2” & 2 ½” branch piping with 6” mains.

The building has various rack storage, mainly dealing with doors and construction materials. There is also a large paint room.

(ORE PAC - Warehouse Expansion) MODIFICATION TO ADD A 2,277 SQ. FT. CANOPY TO THE SOUTH SIDE AND TWO 280 SQ. FT. CANOPIES TO THE NORTH SIDE OF THE BUILDING. For the construction of a 43,719 sq. ft. addition to an existing 63,833 sq. ft. warehouse/manufacturing/office building with work to include the construction of a new 43,719 sq. ft. steel building per the approved plans and the removal of the wall on the east end of the existing structure. Under BLD13-03145 a three hour wall was required on the north side along with three hour opening protectives since the separatin distance to the ajacent building to the north is less than 60' and this is an unlimited area building. The outside of the 3 hour assembly was not required to be completed untill construction of this addition commenced. The exterior portion of the three hour assembly on the existing building is required to be completed prior to occupancy of the addition. NO RACKING IS ALLOWED UNDER THIS PERMIT. ANY RACKING OVER 8 FEET IN HEIGHT REQUIRES A SEPARATE RACKING PERMIT. This is a fully sprinklerd buiding for unlimited area with an alarm system; any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/21/20158/21/20158/21/2015PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection8/7/20158/10/20158/10/2015APART
DetailsJim Page
Trip time for system 1, 50 seconds, trip time for system 2, 52 seconds, still need to verify low air alarm set point.
INSP-Sprinkler Rough-in/Hydro8/6/20158/7/20158/7/2015APART
DetailsJim Page
24 hr test performed/completed on dry systems 1 & 2, Hydrostatic test passed/complete on systems 1 & 2.
INSP-Sprinkler Rough-in8/5/20158/6/20158/6/2015APART
DetailsJim Page
24 hour air test started at 0845, 42 psi on dry system one, 43 psi on dry system two.
INSP-Final Inspection5/7/20155/7/20155/7/2015PPART
DetailsKatie Marron
Riser 4: accelerator installed, flow test passed at 27 sec. Partial final complete, new facility systems complete.
INSP-Final Inspection5/5/20155/6/20155/6/2015PFAIL
DetailsKatie Marron
Flow test requirements were not met for riser 4, requires acceleration device. Water flow timed at 66 seconds, requirement for 4 outlet manifold is 40 seconds. Riser 3 passed with 37 second flow.
INSP-Sprinkler Rough-in5/5/20155/5/20155/5/2015PPART
DetailsKatie Marron
Start of 24hr pressure test; riser 4 only. 42 psig at 12:20 on 5/5/15.
INSP-Final Inspection4/29/20155/1/20155/1/2015ANR
DetailsKatie Marron
FDC is installed. Still missing alarm monitoring, emergency lights, and heating per pervious comments. Additionally 24 hr air test passed on risers 1, 2, 3. Riser 4 did not pass dropped from 43.5 to 40 psig. No inspector test flow has been completed to date.
INSP-Sprinkler Rough-in4/28/20154/30/20154/30/2015PPART
DetailsTim Frost
Pump test went ok. However, the pump room is missing emergency lighting, heater all alarm work. The FDC is not installed. The sprinklers for the pump room were not installed. There was a leak in the union to the jockey pump.

The pump was NOT tested for alarm contacts since no alarm work had been permitted.



Jason// pump and air test- NEEDS Specific time- please call ahead Phone #: ###-####

Schedule pump test for 2:00
INSP-Sprinkler Rough-in4/20/20154/23/20154/24/2015APART
DetailsKatie Marron
Hydrostatic test on all four risers in new warehouse satisfactory completed.
INSP-Sprinkler Rough-in/Hydro4/22/20154/24/20154/23/2015PCANC
DetailsTim Frost
Fire pump test was canceled by the contractor due to lack of power to the fire pump

Jason Phone #: ###-####
INSP-Supply line flush4/20/20154/21/20154/21/2015APART
DetailsKatie Marron
Supply line flush completed satisfactory.