INSP-Final Inspection | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection of fire sprinklers for the parking garage area of the building - PASSED. Contractor cert. of completion signed off and will be emailed to the PDS office.
|
INSP-Final Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection for garage dry pipe systems. Final passed, except for record of completion (ROC) paperwork not completed yet.
|
INSP-Final Inspection | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | FAIL |
Thomas Walsh
|
|
|
Final inspection requested for parking garage permit, however noted dissimilar sprinklers (temp ratings) for several sprinklers located in the stair enclosures. Contractor agreed to inspect all and change out as needed to reflect proper temp. ratings per plans.
|
INSP-Sprinkler Rough-in | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PASS |
Thomas Walsh
|
|
|
Retest of dry pipe system #1 for the north side parking garage. PASSED - tripped within 58 seconds to waterflow.
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | FAIL |
Thomas Walsh
|
|
|
Trip test of dry pipe systems protecting the parng garage. The south system tested OK, wheras the north system did not meet 60 seconds trip test. Suspected some blockage within system. Will retest after the problem is addressed.
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/3/2015 | 8/4/2015 | P | CANC |
Thomas Walsh
|
|
|
Due to time constraints, this inspection could ntot be completed. Will reschedule for 8/4.
|
INSP-Alarm Testing | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | FAIL |
Thomas Walsh
|
|
|
Test of all dry pipe system protecting the parking garage (x2), the attic (x2) and the clubhouse. The systems protecting the attic space on the south side, and the clubhouse tested OK. The other three (3) systems failed the 60 second trip test, and will require accelerators. All tampers tested OK. Low air for the dry systems also not tested this visit.
|
INSP-Alarm Testing | 7/29/2015 | 7/30/2015 | 7/30/2015 | A | PART |
Thomas Walsh
|
|
|
Partial fire alarm interface testing, including all wet pipe systems, except for the clubhouse, including water flows, tampers, etc.
|
INSP-Sprinkler Rough-in | 7/23/2015 | 7/23/2015 | 7/24/2015 | P | PASS |
Jim Page
|
|
|
24 hour air test passed/complete on both dry systems in parking structure.
|
INSP-Sprinkler Rough-in/Hydro | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Jim Page
|
|
|
Hydrostatic test passed/complete on both dry systems covering parking garage, 1st level,
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | CANC |
Jim Page
|
|
|
This is a hydro request for the dry system. Mark is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for two (2) dry pipe systems protecting two halves of the parking garage. PASSED - OK to cover.
|