INSP-Final Inspection | 10/14/2015 | 10/15/2015 | 10/15/2015 | A | PASS |
Thomas Walsh
|
|
|
Final Inspection passed.
|
INSP-Alarm Testing | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PART |
Thomas Walsh
|
|
|
Test of wet-pipe systems for wings E, F & G, including all fire alarm interface testing - waterflows and tamper supervisory signals. All floors etsted OK (within 60 seconds). The trip test of the dry pipe valve protecting the attics of these wings did not flow water within the 60 seconds time limit, therefore an accelerator will have to be installed on thsi system.
|
INSP-Sprinkler Rough-in/Hydro | 9/29/2015 | 9/30/2015 | 9/30/2015 | A | PASS |
Jim Page
|
|
|
200 psi hydrostatic test passed/complete for 3rd floor.
|
INSP-Sprinkler Rough-in/Hydro | 9/25/2015 | 9/28/2015 | 9/28/2015 | P | PART |
Jim Page
|
|
|
200 psi hydrostatic test complete on basement level, 1st floor, 2nd floor and 4th floor. 3rd floor will need to be retested at a later date due to a leak in need of repair.
|
INSP-Sprinkler Rough-in | 9/17/2015 | 9/17/2015 | 9/17/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for wet-pipe systems protecting wings E, F & G - drop lid areas only (all hard lid areas previously inspected), for all floors, except wing G - 1st and 2nd floors - See plans for areas inspected - OK to cover pipe in these areas.
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for hard lids in Bldg G- 1st, 2nd, 3rd floors. See plans for areas inspected today. OK to cover these areas.
|
INSP-Sprinkler Rough-in | 7/17/2015 | 7/20/2015 | 7/20/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for portion of Bldg. F - 4th floor that was previously sheetrocked prior to inspection - 4 heads total, and the 1st floor corridor of Bldg. F. OK to cover pipe in these areas.
|
INSP-Sprinkler Rough-in | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | PART |
Thomas Walsh
|
|
|
RTC wet // Bldg. E - 1st floor, Bldg. F - 2nd, 3rd and 4th floor hard lid corridors and comon rooms off the corridors. NOTE: 4th floor Bldg F had some rooms that were already covered, so could not inspect these areas. Some sheetrock in these rooms will have to be removed to complete inspection of these rooms. See plans for areas inspected and OK to cover for this visit.
|
INSP-Sprinkler Rough-in | 5/6/2015 | 5/6/2015 | 5/6/2015 | P | PART |
Scott Arellano
|
|
|
Area "E" 2nd floor corridors OK to cover.
|
INSP-Sprinkler Rough-in | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PART |
Katie Marron
|
|
|
Hard lids only at 3rd floor hallway and common room ok to cover. Advised that current drops for drop ceiling areas look overspaced, contractor to adjust as needed before RTC for drop ceiling. Storage room by elevator still pending a sprinkler drop.
|
INSP-Sprinkler Rough-in | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | PART |
Katie Marron
|
|
|
Bldg G 1st and 2nd Floor dwelling units only ok to cover. One room on both floors missing a head per plan, verified existing coverage is sufficient. Additional heads (1 each) found (not on plan) to end rooms on 1st floor, OK'd. Additional head added in one room, both floors, to maintain coverage from door header, Ok'd.
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | CANC |
Troy Cobbley
|
|
|
Bldg G 1st and 2nd floor RTC Please call Leroy 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | FAIL |
Katie Marron
|
|
|
Bldg G wet system 2nd Floor , no approval for cover at this time due to significant field modifications, requiring plan resubmittial. Modifications include changes to remote area.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PART |
Forrest France
|
|
|
Overhead inspection for the 3rd floor area G wet system at living units only, including tenting, okayed per as-built plans matching install with the exception of two balconies now covered by dry system.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | CANC |
Forrest France
|
|
|
3rd floor rough to cover . Please call Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/6/2015 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 2/20/2015 | 2/20/2015 | 2/20/2015 | P | PART |
Forrest France
|
|
|
Area F 1st floor living units passed rough-in inspection.
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/18/2015 | 2/19/2015 | P | PART |
Forrest France
|
|
|
Rough-in inspection for the 4th floor area F living units completed.
|
INSP-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | PART |
Forrest France
|
|
|
Rough-in inspection completed for building area F 3rd floor wet system living units only- Main at corridor is not yet installed. As-built drawings verified on site to match installation. Items noted corrected while on site.
|
INSP-Sprinkler Rough-in | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed for the 1st floor area E living units. Record drawings provided to match field work and retained to verify with plan resubmittal as previously agreed.
|
INSP-Sprinkler Rough-in | 1/27/2015 | 1/28/2015 | 1/27/2015 | P | CANC |
Forrest France
|
|
|
3rd floor balcony RTC Call Leroy 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2015 | 1/16/2015 | 1/16/2015 | A | PART |
Forrest France
|
|
|
Cover inspection for 3rd and 2nd floor E wing wet system at living units only- Completed with reviewed as-builts to match field installation per agreement. Need to adjust tenting at the 2" main 3rd floor NW end, noted three branchlines 2nd floor which do not correlate to the actual install. Okayed for 3rd floor cover, 2nd okayed pending accurate drawings.
|
INSP-Sprinkler Rough-in | 1/9/2015 | 1/12/2015 | 1/12/2015 | A | NR |
Forrest France
|
|
|
Bldg E 2nd and 3rd Floor Pls call Leroy 30 mins prior Phone #: ###-#### Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 1/8/2015 | 1/8/2015 | 1/9/2015 | P | FAIL |
Forrest France
|
|
|
Conditions unchanged. Refer to inspection notes dated 1/2/15.
|
INSP-Sprinkler Rough-in | 1/7/2015 | 1/8/2015 | 1/9/2015 | A | FAIL |
Forrest France
|
|
|
Conditions unchanged. Refer to inspection notes dated 1/2/15.
|
INSP-Sprinkler Rough-in | 12/30/2014 | 1/2/2015 | 1/2/2015 | A | FAIL |
Forrest France
|
|
|
Field installation does not match approved drawings. Noted changes to branchlines, number of sprinklers, and head layout compared to the design. - Inspection area wing E third floor.
|
INSP-Sprinkler Rough-in | 12/30/2014 | 12/31/2014 | 12/31/2014 | P | DEFR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/10/2015 | | P | |
Forrest France
|
|
|
Rough to cover 2nd floor F. ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Carter II
|
INSP-Sprinkler Rough-in | 11/26/2014 | 11/26/2014 | | P | |
Forrest France
|
|
|
Matt Phone #: ###-####
|