INSP-Final Inspection | 12/8/2015 | 12/8/2015 | 12/8/2015 | P | PASS |
Jim Page
|
|
|
Fire alarm interface with hood suppression system complete. All fire alarm items tested. Final fire alarm inspection passed/complete.
|
INSP-Final Inspection | 10/27/2015 | 10/30/2015 | 10/30/2015 | A | PART |
Thomas Walsh
|
|
|
Test of fire alarm system for SNF Bldg. K, including water flow and tampers for the fire sprinkler systems (wet and dry). All tested OK. Test of SDs, MPs, FSDs, Duct Detectors for HVAC shutdown ( 5 units), notification devices. All components tested OK. NOTE: Hood and Duct FP system not installed yet, and interface with egress hardware (mag-locks) not tested as these doors and hardware are still being installed. Otherwise, Bldg. K fire alarm system test is completed.
|