INSP-Final Inspection | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/23/2015 | 3/24/2015 | 3/24/2015 | A | FAIL |
Troy Cobbley
|
|
|
Alarm signals register as supervisory and hvac units have not been turned on to verify duct smoke detector shut down. No electric alarm bell has been installed to flow switch.
|
INSP-Final Inspection | 3/20/2015 | 3/23/2015 | 3/23/2015 | A | CANC |
Troy Cobbley
|
|
|
Scheduled for wrong day.
|
INSP-Alarm Testing | 3/20/2015 | 3/20/2015 | 3/20/2015 | A | DONE |
Troy Cobbley
|
|
|
Was only able to verify monitoring (phone lines) and supervision of the 4009 NAC panel. No one could verify the the hvac units are functional and the sprinkler contractor was not available.
|
INSP-Alarm Testing | 3/18/2015 | 3/18/2015 | 3/18/2015 | P | DONE |
Troy Cobbley
|
|
|
Todays inspection was only to verify horn/strobe function. All audio/visuals operated correctly.
|
INSP-Conference | 3/10/2015 | 3/11/2015 | 3/11/2015 | A | DONE |
Troy Cobbley
|
|
|
Brian and I went over possible problem area where there is a lack of strobe coverage. Plan modifications will be required due to NAC panel configuration changes
|