DOC - Permit Finaled | | | 1/8/2019 | | DONE |
Lee G Meredith
|
|
|
|
INSP-Final Inspection | 10/29/2015 | 10/29/2015 | 10/29/2015 | P | PASS |
Thomas Walsh
|
|
|
Fire alarm system testing for Garage #2 passed test/inspection.
|
INSP-Final Inspection | 10/21/2015 | 10/26/2015 | 10/26/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm system test of wings F & G, including all unit SDs. corridor SDs, manual pulls, notification devices (audibility), FSDs, elevator recall functions, etc. All tested OK. Two unit SDs had to be reprogrammed to activate correctly. NOTE: All fire sprinkler system testing completed with wing E test.
|
INSP-Alarm Testing | 10/6/2015 | 10/6/2015 | 10/6/2015 | P | PART |
Thomas Walsh
|
|
|
Trip test of dry pipe valve for wings EF&G attics, including low-air alarm, tamper and pressure switch - all tested OK. NOTE: Elevatorfor wing E was not tested - recall functions not operating due to some fault in the elevator system. Will retest after elevator is functioning properly. Note2: There are a couple of FA devices at the separation between Wing E & F, that need to be functional for TCO of wing E. Contractor agreed to rewire these devices to make them operational for Wing E TCO.
|
INSP-Final Inspection | 10/1/2015 | 10/5/2015 | 10/5/2015 | A | PART |
Thomas Walsh
|
|
|
Test of fire alarm system for wing E - all floors including a portion of the parking garage system, includingt test of all in-room smoke detectors, corridor SDs, manual pulls, SFDs, waterflows and tampers. All tested OK, except for the dry-pipe attic sprinkler system which will have to be retested after an accelerator device is added to this system. NOTE: Wings F & G not ready for testing yet, although there are a few devices in bldg. F that will have to be made functional as they are located in the wing E TCO area. Also, elevator testing for this wing not performed yet - the state is scheduled to conduct their test tomorrow.
|