INSP-Final Inspection | 11/2/2015 | 11/3/2015 | 11/3/2015 | P | PASS |
Jim Page
|
|
|
Design placards in place, inspection passed/complete
|
INSP-Final Inspection | 10/27/2015 | 10/29/2015 | 10/29/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection of fire sprinkler systems for Bldg. K, including wet and dry pipe systems, and fire alarm interface, including water flows, tampers, wet and dry pipe flow tests, completion of 24 hour air test of dry pipe system. All tested OK. Dry pipe system did not activate exterior alarm bell when tested, but this was corrected. Design placards need to be installed on risers.
|
INSP-Sprinkler Rough-in | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | PART |
Thomas Walsh
|
|
|
Started 24 hour air test of dry pipe fire sprinkler system for Bldg. K. Will reinspect tomorrow same time (9:00am) to confirm holding after 24 hours.
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest and RTC inspection for Bldg. K wet-pipe system (200psi @ 2hrs). PASSED = OK to cover pipe for this system.
|
INSP-Sprinkler Rough-in | 7/27/2015 | 7/27/2015 | 7/27/2015 | P | PART |
Jim Page
|
|
|
Notated area's inspected and approved for cover with red ink on city approved drawings
|
INSP-Sprinkler Rough-in/Hydro | 6/17/2015 | 6/17/2015 | 6/18/2015 | P | PASS |
Thomas Walsh
|
|
|
Bldg K - Hydrotest of dry pipe system - 200 psi @ 2hours - PASSED
|
INSP-Sprinkler Rough-in | 3/27/2015 | 3/27/2015 | 3/31/2015 | P | PART |
Forrest France
|
|
|
Inspection to verify completion of previously noted correction items at the dry system. Finished 3/27.
|
INSP-Sprinkler Rough-in | 3/23/2015 | 3/23/2015 | 3/31/2015 | P | PART |
Forrest France
|
|
|
Overhead inspection completed for the dry system and single line feeds to individual sprinklers at some perimeter rooms fed from the wet system. Refer to approved plans for locations in need of revison including spacing, obstructions, and seismic bracing.
|