Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR14-00751
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 4032 S COUNCIL SPRING RD
Project NameTerraces of Boise Bldg L
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting skilled nursing L. Residential sprinklers, concealed space sprinklers and quick response sprinklers are being utilized. There is a dry and wet system.

The underground was installed under permit FIR14-00071

The Terraces of Boise - Skilled Nursing Cottage L - To construct a new 12,465 square foot, one story, wood framed skilled nursing facility and related site improvements. This nursing home will contain 16 sleeping units with individual restrooms, as well as, a kitchen, dining and hearth room social area. This building will also contain a hair salon, laundry, storage and mechanical areas. This building is divided into two smoke compartments by a one-hour smoke barrier wall. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/16/201512/16/201512/16/2015PPASS
DetailsJim Page
Dry system hydrostatic test completed under FIR14-00071, fire sprinkler inspections passed/complete for building L
INSP-Sprinkler Rough-in/Hydro12/10/201512/16/201512/16/2015PCANC
DetailsJim Page
Inspection request for a final inspection, cancelling this inspection request and generating a new final inspection request.
INSP-Final Inspection12/10/201512/11/201512/10/2015PCANC
DetailsJim Page
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Final Inspection12/10/201512/11/201512/10/2015PCANC
DetailsJim Page
Bldg L Final and trip test
Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Sprinkler Rough-in12/9/201512/10/201512/10/2015PPASS
DetailsJim Page
24 hour air test for dry system passed/complete. 200 psi hydrostatic test still needs to be completed.
INSP-Sprinkler Rough-in12/9/201512/9/201512/9/2015PPART
DetailsJim Page
24 hour air test started at 1330 hours @ 40psi.
INSP-Sprinkler Rough-in/Hydro9/2/20159/3/20159/3/2015APASS
DetailsThomas Walsh
Hydrostatic test (200 psi @ 2hours) for the wet pipe system for Bldg. L. Some hard-lid areas of the wet system have already been covered, although contractor has stated that these areas were inspected prior to this inspection. No inspection of these areas were recorded on the plans, which is the typical process.
Hydrotest PASSED
INSP-Sprinkler Rough-in9/2/20159/3/20159/3/2015APART
DetailsThomas Walsh
Rough to cover inspection for wet pipe hard lids - some CPVC pipe already covered - contractor stated that was inspected at an earlier inspection, although this was not indicated on the plans. Wet system under hydrotest also during this inspection.
INSP-Sprinkler Rough-in/Hydro6/25/20156/25/20156/25/2015PPART
DetailsThomas Walsh
RTC inspection for dry pipe system for Bldg.L - PASSED - OK to cover piping.
NOTE: Hydrotest will performed at a later date.