INSP-Final Inspection | 12/16/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Jim Page
|
|
|
Dry system hydrostatic test completed under FIR14-00071, fire sprinkler inspections passed/complete for building L
|
INSP-Sprinkler Rough-in/Hydro | 12/10/2015 | 12/16/2015 | 12/16/2015 | P | CANC |
Jim Page
|
|
|
Inspection request for a final inspection, cancelling this inspection request and generating a new final inspection request.
|
INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 | P | CANC |
Jim Page
|
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 | P | CANC |
Jim Page
|
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 12/9/2015 | 12/10/2015 | 12/10/2015 | P | PASS |
Jim Page
|
|
|
24 hour air test for dry system passed/complete. 200 psi hydrostatic test still needs to be completed.
|
INSP-Sprinkler Rough-in | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PART |
Jim Page
|
|
|
24 hour air test started at 1330 hours @ 40psi.
|
INSP-Sprinkler Rough-in/Hydro | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Thomas Walsh
|
|
|
Hydrostatic test (200 psi @ 2hours) for the wet pipe system for Bldg. L. Some hard-lid areas of the wet system have already been covered, although contractor has stated that these areas were inspected prior to this inspection. No inspection of these areas were recorded on the plans, which is the typical process. Hydrotest PASSED
|
INSP-Sprinkler Rough-in | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for wet pipe hard lids - some CPVC pipe already covered - contractor stated that was inspected at an earlier inspection, although this was not indicated on the plans. Wet system under hydrotest also during this inspection.
|
INSP-Sprinkler Rough-in/Hydro | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for dry pipe system for Bldg.L - PASSED - OK to cover piping. NOTE: Hydrotest will performed at a later date.
|