INSP-Final Inspection | 10/14/2015 | 10/15/2015 | 10/15/2015 | A | PASS |
Thomas Walsh
|
|
|
Final Inspection passed. Certificates of Completion forms to be submitted electronically.
|
INSP-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 | P | PART |
Thomas Walsh
|
|
|
Trip test of dry-pipe system protecting the attic spaces above wings E, F & G. The system failed its test yesterday, so the contractor installed an accelerator to improve its activation. Retest passed - water delivered within 60 seconds.
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2015 | 10/2/2015 | 10/4/2015 | P | PASS |
Thomas Walsh
|
|
|
Completed 24 hour air test of dry pipe system for wings E, F & G - PASSED NOTE: Hydrotest of all wet pipe and dry systems for these wings have been completed. Fire alarm interface testing required prior to final acceptance.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2015 | 10/1/2015 | 10/1/2015 | P | PART |
Thomas Walsh
|
|
|
Bldg EFG dry pipe system air test (start) 42 psi @ 1300 hrs.
|
INSP-Sprinkler Rough-in/Hydro | 9/25/2015 | 9/28/2015 | 9/28/2015 | P | PART |
Jim Page
|
|
|
200 psi hdrostatic test complete on dry system, 24 hour air test still needs to be completed.
|
INSP-Sprinkler Rough-in/Hydro | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | PART |
Forrest France
|
|
|
Verified plan modifications. Dry system area G upper and lower levels plan sheet 3 okayed for cover.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | FAIL |
Forrest France
|
|
|
Area G dry system install does not correlate with approved plan set regarding main routing.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/19/2015 | 3/19/2015 | P | CANC |
Forrest France
|
|
|
3rd floor rough to cover Please call Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/6/2015 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 12/30/2014 | 1/2/2015 | 1/2/2015 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection for the dry system area E third floor. Noted one missing seismic brace. A portion of framing/blocking at eaves to remain open to ensure adequate coverage.
|
INSP-Sprinkler Rough-in | 12/30/2014 | 12/31/2014 | 12/31/2014 | P | DEFR |
Forrest France
|
|
|
|