INSP-Final Inspection | 12/28/2015 | 12/28/2015 | 12/28/2015 | P | PASS |
Jim Page
|
|
|
Tampers and flow switches tested for 2nd and 3rd floor, devices tested okay and were put into service.
|
INSP-Final Inspection | 12/23/2015 | 12/28/2015 | 12/28/2015 | A | CANC |
Jim Page
|
|
|
Called POC listed for project, Raul phone# ###-####, POC is on vacation out of the country, this inspection request is cancelled and the contractor will need to reschedule inspection request.
|
INSP-Final Inspection | 12/23/2015 | 12/28/2015 | 12/23/2015 | A | CANC |
Jim Page
|
|
|
TOB bldg. H final Please call Leroy 30 min prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Final Inspection | 12/17/2015 | 12/17/2015 | 12/17/2015 | P | CANC |
Jim Page
|
|
|
Contractor will reschedule to coincide with alarm inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2015 | 11/6/2015 | 11/6/2015 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test passed/complete for bldg H basement level, 1st floor, 2nd floor and 3rd floor.
|
INSP-Sprinkler Rough-in | 10/26/2015 | 10/27/2015 | 10/27/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for Bldg. H 3rd floor drop ceiling lids. PASSED NOTE: This completes the rough inspection for the entire 3rd fllor. OK to cover pipe on thi floor.
|
INSP-Sprinkler Rough-in | 10/14/2015 | 10/15/2015 | 10/15/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection of second floor drop ceiling drops. All areas inspected OK - see plans for areas inspected - This inspection completes rough insp. for the second floor - hydrotest and final inspections to be performed at a later date.
|
INSP-Sprinkler Rough-in | 9/21/2015 | 9/22/2015 | 9/22/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for Bldg. H 1st floor - drop tile areas only. PASSED NOTE: All hard lids for this floor already inspected, therefore rough inspection for this entire floor is completed.
|
INSP-Sprinkler Rough-in | 9/14/2015 | 9/14/2015 | 9/14/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for Bldg. H basement. See plans for areas inspected this visit. NOTE: Two (2) SSU sprinklers located at the elevator lobby obstructed by grid mounted lighting units that exceeds 4ft in one dimension. Modify these sprinklers as needed, or remove the obstructions to these sprinklers.
|
INSP-Sprinkler Rough-in | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for hard lid areas on the 3rd floor of Bldg. H. See plans for areas inspected this visit. OK to cover pipe in these areas.
|
INSP-Sprinkler Rough-in | 8/7/2015 | 8/10/2015 | 8/10/2015 | A | PART |
Thomas Walsh
|
|
|
Re-inspection of fire caulking of 3rd floor Bldg. H - RTC inspection. All penetrations adequately fire caulked. OK to cover pipe in this area - see plans for areas (rooms) inspected.
|
INSP-Sprinkler Rough-in | 8/7/2015 | 8/7/2015 | 8/7/2015 | P | FAIL |
Thomas Walsh
|
|
|
RTC inspection for Bldg. H 3rd floor hard lids. Conversation about fire-caulking transpired. Called Jim Storey to confirm requirements. Jim stated that fire cauling required for all wall penetrations between the rooms and the corridor, as well as the walls separating the unit rooms. Therefore, more caulking is required, as many of the walls separating units were not fire caulked. Will reschedule when completed.
|
INSP-Sprinkler Rough-in | 8/7/2015 | 8/7/2015 | 8/7/2015 | P | CANC |
Thomas Walsh
|
|
|
TOB Bldg H wet RTC Please call Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for hard lid areas for the 2nd floor - Bldg H. See plans for areas inspected. OK to cover piping inspected today.
|
INSP-Sprinkler Rough-in | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | PART |
Jim Page
|
|
|
RTC inspection for Bldg H 2nd floor hard lid areas - see plans for areas inspected today. OK to cover pipe in these areas.
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for Bldg H basement and first floor hard lid areas - see plans for areas inspected today. OK to cover pipe in these areas.
|
INSP-Sprinkler Rough-in | 7/14/2015 | 7/14/2015 | 7/14/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for Bldg H wet pipe system for 3rd floor (2nd floor above grade) for units only - see plans for areas inspected today. OK to cover these areas.
|
INSP-Sprinkler Rough-in | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for Bldg H wet system for first and second floors - hard lid areas - see plans for areas inspected. Also Bldg H first floor feed main provides protection for the bulk feed main that supplies wings A-D, that are completed and in service.
|
INSP-Sprinkler Rough-in | 6/17/2015 | 6/17/2015 | 6/18/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for 1st floor Bldg. H hard lid areas - see plans for areas inspected.
|
INSP-Sprinkler Rough-in | 6/5/2015 | 6/8/2015 | 6/8/2015 | A | PART |
Thomas Walsh
|
|
|
Hard lid rough inspection for Bldg. H wet pipe system - see plans for areas inspected. OK to cover these areas.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/1/2015 | 6/1/2015 | P | PART |
Thomas Walsh
|
|
|
Hydrotest (partial) of Bldg H basement and first floor portions of the system needed for TCO of Bldgs A-D Phase 1 TCO. 200psi @ 2 hours - PASSED
|
INSP-Sprinkler Rough-in | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PART |
Thomas Walsh
|
|
|
Rough in inspection of Bldg. H -basement hard lid areas.
|
INSP-Supply line flush | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | CANC |
Forrest France
|
|
|