INSP-Final Inspection | 1/10/2019 | 1/16/2019 | 1/16/2019 | P | CANC |
Jim Page
|
|
|
Final fire sprinkler inspection for core and shell was complete under FIR18-00718.
Antonio Phone #: ###-####
|
DOC - Permit Finaled | | | 1/16/2019 | | DONE |
|
|
|
per jim page
|
INSP-Final Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 | P | PART |
Jim Page
|
|
|
Contractor/Tenant is looking for a partial final for exterior of building in regards to the fire sprinkler system, previously noted items repaired, fire sprinklers inspection for exterior fire sprinklers passed/complete. Fire sprinkler system in service.
|
INSP-Final Inspection | 11/4/2015 | 11/4/2015 | 11/4/2015 | P | FAIL |
Jim Page
|
|
|
Contractor/Tenant is looking for a partial final for exterior of building in regards to the fire sprinkler system, wire conduit connections going to PIV tamper switch are not weather proof fittings, contractor installed flex conduit to hard pipe and used electrical tape for connection, not a weather tight fitting. Fire sprinkler systems are isolated at backlow, no active fire sprinkler systems at time of inspection. Backflow needs a current backlow inspection/tag for fire system. Wet system fire sprinkler pipng on the west side of building, patio area has heat tape installed and monitored but no piping insulation is installed, need to have insulation installed before sprinkler system is put into service/covered. Escutcheon's missing on first floor dry fire sprinkler heads, escutcheon's need to installed before next partial final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PART |
Katie Marron
|
|
|
Hydrostatic pressure test complete all three risers/systems. Basement system failed first attempt. Leaking vic in main area was adjusted/tightened on the spot. Basement system was pumped back up for a second test and passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/30/2015 | 4/30/2015 | 4/30/2015 | P | CANC |
Katie Marron
|
|
|
Cancelled due to inspection load
|
INSP-Sprinkler Rough-in | 4/1/2015 | 4/2/2015 | 4/2/2015 | P | PART |
Forrest France
|
|
|
Initial walkthrough completed- items noted include; overspaced coverage at one location in the basement, DSW not yet installed at the basement, PIV and FDC must remain accessible, heat trace and insulation fill at the combustible concealed space grade level not yet complete, provide an intermediate temp head below the second floor skylight.
________________
Add by TRF 4/06/2015
The sprinkler in the opening on the porch is incorrect it is a QR pendent. The sprinkler is supposed to be a horizontal sidewall spraying DOWN to create a water curtian affect.
|