INSP-Final Inspection | 5/18/2015 | 5/19/2015 | 5/20/2015 | P | PASS |
Thomas Walsh
|
|
|
Fire sprinkler system final - PASSED. All alarm connections tested OK. ROC and as-built plans provided.
|
INSP-Final Inspection | 5/15/2015 | 5/18/2015 | 5/18/2015 | P | CANC |
Troy Cobbley
|
|
|
Fire alarm not ready, rescheduled for 19MAY2015
|
INSP-Final Inspection | 5/14/2015 | 5/15/2015 | 5/15/2015 | P | NR |
Katie Marron
|
|
|
Alarm monitoring was not ready, so we could not complete final sprinkler inspection/flow testing.
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Troy Cobbley
|
|
|
OH/Hydro passed
|
INSP-Sprinkler Rough-in | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PART |
Troy Cobbley
|
|
|
OH/Hydro failed due to another contractor messing with a control valve. Previous corrections have been addressed and remaining piping can be covered.
|
INSP-Supply line flush | 5/6/2015 | 5/7/2015 | 5/7/2015 | P | PASS |
Katie Marron
|
|
|
Supply line flush completed satisfactory. Rough in inspection completed, ok to cover with the following exceptions: missing drop/ceiling grid, 4 missing hangars, 1 overspaced sprinkler and 2 missed coverage areas requiring additional head. Marked plan sheet with locations.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed. Preliminary inspection of the overhead piping also finished.
|