INSP-Final Inspection | 7/6/2017 | 7/7/2017 | 7/6/2017 | A | PASS |
Jim Page
|
|
|
Final inspection for fire sprinklers completed on 6/22/2015.
|
INSP-Final Inspection | 6/22/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Katie Marron
|
|
|
Additional head installed to cover obstructed area. Scope of work complete. Permit finaled.
|
INSP-Final Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 | P | PART |
Katie Marron
|
|
|
Final pending corrections to obstructed head in vehicle bay.
|
INSP-Supply line flush | 6/2/2015 | 6/3/2015 | 6/3/2015 | A | PASS |
Katie Marron
|
|
|
Underground flush of new 4" main completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2015 | 5/27/2015 | 5/27/2015 | P | PASS |
Jim Page
|
|
|
Underground hydrostatic test complete/passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2015 | 3/18/2015 | 3/18/2015 | P | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed. Need to verify insulation fill above the vehicle bay at the non-sprinklered combustible concealed spaces to meet allowable exceptions per NFPA 13, need to relocate one overspaced upright above the report room. OH hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/16/2015 | 3/17/2015 | 3/17/2015 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 3/12/2015 | 3/12/2015 | 3/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground ok to cover. All land scaping to be level with the sidewalk or the minimum 4'6" won"t be met
|
INSP-Sprinkler Rough-in | 3/11/2015 | 3/11/2015 | 3/12/2015 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Rescheduled for 3/12/2015
|
INSP-Sprinkler Rough-in | 2/23/2015 | 2/23/2015 | 2/23/2015 | P | PART |
Forrest France
|
|
|
The 4" IBR only, inspected for cover at this time. *NOTE- thrust blocking is not provided- contractor has choosen to utilize rodding method.
|