INSP-Final Inspection | 6/19/2015 | 6/22/2015 | 6/22/2015 | A | PASS |
Jim Page
|
|
|
Previously noted items corrected, fire alarm inspection/test passed/complete
|
INSP-Final Inspection | 6/16/2015 | 6/17/2015 | 6/17/2015 | A | FAIL |
Jim Page
|
|
|
Contractors scope of work complete, end of line voltage verifyed and acceptable. Horns and strobes from contractors scope to main floor as well as other area's on main floor are not synced together, flashing and sounding at different times. Contractor is aware of issue, instructed the on site point of contact, Randy, phone ####-#### will not final until issue is addressed/corrected.
|
INSP-Final Inspection | 6/3/2015 | 6/9/2015 | 6/9/2015 | A | FAIL |
Jim Page
|
|
|
City approved plans not on site.
|
INSP-Final Inspection | 5/14/2015 | 5/19/2015 | 5/19/2015 | A | FAIL |
Troy Cobbley
|
|
|
Lack of strobe coverage in front of pharmacy, discussed solution with contractor to correct said issue, will need to provide as build drawings.
|
INSP-Final Inspection | 4/28/2015 | 5/5/2015 | 5/5/2015 | A | DEFR |
Katie Marron
|
|
|
To be rescheduled per phone call with alarm company representative to accomodate store request for alarm test at 730am.
|