INSP-Final Inspection | 9/30/2015 | 10/1/2015 | 10/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/29/2015 | 9/30/2015 | 9/30/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need to forward flush test the backflow, need cap on the FDC connection, need back flow certification and need the pressure relief vavle.
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | CANC |
Troy Cobbley
|
|
|
Underground hydo test already passed
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/19/2015 | 8/19/2015 | P | PASS |
Jim Page
|
|
|
Overhead hydrostatic test passed/complete, do not see any comments for underground hydrostatic test, underground still needs hydrostatic test.
|
INSP-Sprinkler Rough-in | 8/18/2015 | 8/19/2015 | 8/19/2015 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection passed/complete, entire project approved for cover.
|
INSP-Sprinkler Rough-in | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PASS |
Troy Cobbley
|
|
|
The rough in inspection for 4 dry heads in the chases passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 7/8/2015 | 7/9/2015 | 7/9/2015 | A | PASS |
Troy Cobbley
|
|
|
Lobby sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/8/2015 | 7/8/2015 | 7/8/2015 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations (hard lids) where the piping is marked "ok" for cover. Main Lobby is ok to cover as well.
|
INSP-Supply line flush | 7/6/2015 | 7/6/2015 | 7/6/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | FAIL |
Troy Cobbley
|
|
|
I left message on voice mail I was on the way. Got to job site and could not make contact with contractor. No flush performed.
|
INSP-Supply line flush | 6/29/2015 | 6/30/2015 | 6/30/2015 | P | PART |
Troy Cobbley
|
|
|
No underground flush performed. Underground hydro passed
|
INSP-Sprinkler Rough-in | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground piping okay for cover
|