INSP-Final Inspection | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2015 | 10/1/2015 | 10/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | FAIL |
Troy Cobbley
|
|
|
United water has not opened the valve. No flush performed.
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2015 | 9/23/2015 | 9/23/2015 | A | PASS |
Troy Cobbley
|
|
|
underground hydro test passed
|
INSP-Supply line flush | 9/17/2015 | 9/17/2015 | 9/17/2015 | P | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 9/9/2015 | 9/10/2015 | 9/10/2015 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number scheduled
|
INSP-Sprinkler Rough-in | 8/26/2015 | 8/27/2015 | 8/27/2015 | A | PASS |
Troy Cobbley
|
|
|
Piping above the restrooms and janitors closet is ok to cover.
|
INSP-Supply line flush | 5/7/2015 | 5/7/2015 | 5/7/2015 | P | PASS |
Troy Cobbley
|
|
|
In building riser and 9' pf 8" underground supply piping is ok to cover.
|