Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberFIR15-00398
StatusIssued
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 529 E PARKCENTER BLVD
Project NameThe District: Cottages # A-1
Customer NumberUDG ONLY
ePlanReviewYes
Description
[The District - Cottage Building A - #1 - Udg Only] - Quick Permit
Connect to the new 4" gate valve and install new 4" C900 UG pipe into the new building for a fire sprinkler system per NFPA 13R, 2013 and the City of Boise.

(THE DISTRICT AT PARKCENTER - COTTAGE BUILDING A - #1) (The drawings are filed under permit BLD14-01818 in ePlanReview) To construct a 10 dwelling unit two story apartment building with each unit having its own garage (i.e. 10 garages). The total floor area of this building is about 14,708 square feet (8,374 square feet 1st story and 6,334 square feet 2nd story). All ground floor units are required to comply as Type B units. Two of those ground floor units within Cottage Building A - #2 are required to comply as Type A units. Work is to include interior nonbearing walls, 1-hr bearing walls, 1-hr roof-ceiling assemblies, 1-hr floor-ceiling assemblies, 1-hr dwelling unit separations, attic insulation, interior doors, exterior windows and doors, insulated exterior walls, “Hardi-board” exterior siding, exterior manufactured stone wainscot, composition roof shingles, common stairways within a 1-hr corridor, private interior stairways, garages, garage overhead doors, millwork, and finishes. Structural work includes concrete footings, concrete stem walls, concrete floor slabs on grade with thickened footings at interior bearing walls, wood floor trusses, wood roof trusses, wood columns, wood beams, and shear walls. Special inspection is required for soils, concrete, and wood. The designs for the roof trusses and floor trusses are deferred submittal items. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13R as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Supply line flush5/25/20165/27/20165/27/2016ACANC
DetailsJim Page
Inspection request cancelled, could not flush this underground due to road valve box damage, flush will be rescheduled when road box is repaired.
INSP-Sprinkler Rough-in/Hydro5/24/20165/25/20165/25/2016APASS
DetailsJim Page
200 psi hydrostatic test complete for underground supply.
INSP-Sprinkler Rough-in2/10/20162/10/20162/10/2016PPASS
DetailsJim Page
Rough to cover inspection passed/complete for the underground fire sprinkler supply line, underground approved for cover.