INSP-Final Inspection | 11/3/2015 | 11/3/2015 | 11/3/2015 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Final Inspection | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | PART |
Troy Cobbley
|
|
|
A temporary is being given until the Remstar unit has been installed and sprinkler protection provided. All other sprinkler work is complete.
|
INSP-Sprinkler Rough-in | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection passed/complete, approved for cover.
|
INSP-Sprinkler Rough-in | 8/26/2015 | 8/26/2015 | 8/26/2015 | A | PART |
Jim Page
|
|
|
Inspected mains and branch-lines, fire sprinkler heads will be cut in when finish ceiling is installed, will need to perform rough to cover inspection when heads are installed.
|