INSP-Final Inspection | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | PASS |
Troy Cobbley
|
|
|
EQ Bracing has been installed
|
INSP-Sprinkler Rough-in | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PART |
Troy Cobbley
|
|
|
Missing nearly all of the earth quake bracing. Piping can be covered but upon return inspection areas will have to be removed to facilitate re-inspection of the bracing.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/6/2015 | 10/6/2015 | P | PASS |
Jim Page
|
|
|
24 hour air test passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PART |
Jim Page
|
|
|
200 psi hydrostatic test passed/complete. 24 hour air test started at 3:30pm at 50 psi.
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2015 | 9/23/2015 | 9/23/2015 | P | CANC |
Troy Cobbley
|
|
|
24 hour air Phone #: ###-#### Inspection requested via web by John Venche
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | CANC |
Troy Cobbley
|
|
|
Not ready for hydro yet
|
INSP-Sprinkler Rough-in | 9/15/2015 | 9/15/2015 | 9/15/2015 | P | PASS |
Troy Cobbley
|
|
|
Overhead piping rough-in passed. Just missing the earth quake bracing on the relocated 4" main. Riser not built yet.
|
INSP-Sprinkler Rough-in | 9/14/2015 | 9/15/2015 | 9/15/2015 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. I did walk with Bruce and noted missing branch line restraints
|