INSP-Final Inspection | 10/26/2016 | 10/28/2016 | 10/28/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Jim Page
|
|
|
24 hour air test for the 2 parking garage dry systems complete.
|
INSP-Sprinkler Rough-in | 10/10/2016 | 10/11/2016 | 10/11/2016 | P | CANC |
Jim Page
|
|
|
Hydrostatic test for remaining wet systems will be rescheduled to coincide with 24 hour air est completion.
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2016 | 10/11/2016 | 10/11/2016 | P | PART |
Jim Page
|
|
|
24 hour air test for both dry systems started at 10:00AM
|
INSP-Sprinkler Rough-in | 6/9/2016 | 6/10/2016 | 6/10/2016 | A | PART |
Jim Page
|
|
|
Rough in inspection for attic system complete, attic system approved for cover.
|
INSP-Sprinkler Rough-in | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 3 complete, overhead fire sprinkler piping located above hardlids on level 3 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2016 | 5/9/2016 | 5/9/2016 | P | CANC |
Jim Page
|
|
|
Spoke to point of contact provided, Colton Phone #: ###-#### , inspection requests were to be cancelled and resheduled for a later date. Cancelling this inspection request based on conversation with point of contact.
|
INSP-Sprinkler Rough-in | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | CANC |
Jim Page
|
|
|
Rough to cover inspection cannot be completed at this time. Fire sprinkler plans may need to be resubmitted/approved, until this is finalized, no area's can be covered. This inspection request cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test, 2hrs @ 200psi passed/complete for 3rd level.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/25/2016 | 2/25/2016 | P | PASS |
Jim Page
|
|
|
First floor dry system hydrostatic test passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2016 | 2/24/2016 | 2/24/2016 | P | PART |
Jim Page
|
|
|
2nd floor dry system hydrostatic test passed/complete. 1st floor dry system hydrostatic test failed due to system leakage. will need retested at later date.
|
INSP-Supply line flush | 2/15/2016 | 2/16/2016 | 2/16/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for underground hydro/flush, underground permit issued under FIR15-00235. Inspection request for underground flush/hydro under this FIR permit cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 2/15/2016 | 2/16/2016 | 2/16/2016 | A | CANC |
Jim Page
|
|
|
Inspection request was for underground hydro/flush, underground permit issued under FIR15-00235.
|
INSP-Sprinkler Rough-in | 1/27/2016 | 1/29/2016 | 1/29/2016 | P | PART |
Jim Page
|
|
|
Rough in inspection complete for first floor and second floor, notated the city approved drawings with red ink/yellow high-lighter area's inspected and approved for cover. Inspected apartments on third level, high-lighted city approved drawings with yellow the sprinkler branchlines that were inspected and approved for cover.
|
INSP-Sprinkler Rough-in | 1/26/2016 | 1/27/2016 | 1/27/2016 | P | CANC |
Jim Page
|
|
|
Spoke with point of contact Matt, phone number ###-####, requested to have the inspection rescheduled due to scheduling conflict for today. Matt said that was acceptable and will reshedule inspection request.
|