Permit Information
Permit NumberFIR15-00602
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1099 W FRONT ST
Project NameSimplot World Headquarters
Customer Number 
ePlanReviewYes
Description
[Simplot World Headquarters - Level 1 Office and Levels 1 and 2 Annex]
The fire sprinkler scope of work consists of protecting a 9-story structure (Office) and adjoining 5-story structure (Annex). This review is for level 1 of the office structure and levels 1 and 2 of the annex structure. This submittal also encompasses a 1000 Gpm @ 149 Psi fire pump and two 8” underground supply mains from two different city mains. There are standpipes throughout however; they are not being submitted at this time. There are dry pipe as well as wet system. The design is based on light and ordinary hazard II. There are some wet mains that run through freezing areas. The wet mains are being protected from freezing by a listed heat tracing system. (Since the fire protection system is dependent upon the heat tracing system, this permit cannot be approved until the heat tracing system is submitted and approved)

SIMPLOT OFFICE Tenant Improvement - This permit is to finish a new 306,345 square foot, nine story office building for occupancy. The first floor will have a large lobby area, customer experience area and office and training areas. There will be a wellness center at the south end of the main building. Separate tenant improvement permits will be required to finish the future coffee shop, incubator space and future restaurant at the first floor of the annex. The second floor of the main building will be office space. The second floor of the annex will have a large lobby, a multipurpose assembly room and an auditorium. The third floor of the main building will be office space. The fourth floor of the main building will be office space. The fourth floor of the annex is a restaurant with a full kitchen and large exterior patio seating area. The fifth floor of the main building will be office space. The fifth floor of the annex has a kitchen, office areas and a greenhouse. The greenhouse structure is deferred and has not been reviewed or approved. The sixth floor will be office space with an exterior deck at the south end of the floor. The seventh floor will be office space with a large conference room, a kitchen and exterior decks at the east and west ends of the floor. The eighth floor will be office space. The ninth floor will be office space. The core areas were completed under the shell and core permit BLD14-02173. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/7/20173/7/20173/7/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection11/15/201611/15/201611/15/2016PPART
DetailsJim Page
Final fire sprinkler inspection for levels 1 & 2 of annex complete. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
INSP-Final Inspection10/20/201610/20/201610/20/2016PPART
DetailsJim Page
Final fire sprinkler inspection for level 1 simplot tower complete. This FIR permit is associated with levels 1 and 2 of the annex building, final inspection needs to be completed for the annex before this permit can be finaled. This FIR permit will also stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
INSP-Final Inspection10/17/201610/17/201610/17/2016PCANC
DetailsJim Page
Inspection request rescheduled for 18OCT2016
INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016PPART
DetailsJim Page
24 hour air test for dry systems associated with this permit started at 11:00AM (Total of 7 dry systems in test for 24 hours)
INSP-Sprinkler Rough-in/Hydro9/28/20169/29/20169/29/2016PCANC
DetailsJim Page
Level 1 not ready for hydrostatic test, hydro will be rescheduled for another day.
INSP-Sprinkler Rough-in9/15/20169/21/20169/21/2016PDONE
DetailsJim Page
Fire pump start up complete
INSP-Sprinkler Rough-in/Hydro9/15/20169/16/20169/16/2016ACANC
DetailsJim Page
Hydrostatic test cancelled per conversation with point of contact, Jeff ###-####. Hydrostatic test will be rescheduled after system will hold test.
INSP-Sprinkler Rough-in9/12/20169/12/20169/12/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located on the west side level 1 wing complete, including shell protection for future tenant area, level 1 west wing overhead fire sprinkler piping approved for cover. Rough to cover inspection for overhead fire sprinkler piping located on the north side level 1 lobby area complete, overhead fire sprinkler piping located on north level 1 lobby approved for cover.
INSP-Sprinkler Rough-in/Hydro7/12/20167/13/20167/13/2016PPASS
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on levels 1 and 2 complete.
INSP-Sprinkler Rough-in7/6/20167/7/20167/7/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on levels 1 and 2 of the annex building complete, overhead fire sprinkler piping on levels 1 and 2 of the annex building approved for cover.
INSP-Sprinkler Rough-in/Hydro5/10/20165/11/20165/11/2016APASS
DetailsJim Page
Northwest underground supply hydrostatic test complete, this completes underground hydrostatic tests.
INSP-Supply line flush5/4/20165/10/20165/10/2016ADONE
DetailsJim Page
Underground supply flush complete, both supply mains have now been flushed.
INSP-Sprinkler Rough-in/Hydro4/18/20164/18/20164/18/2016PPART
DetailsJim Page
Southwest underground supply hydrostatic test complete, noorthwest hydro will be completed after underground flush is complete.
INSP-Supply line flush4/8/20164/12/20164/12/2016APART
DetailsJim Page
Southwest side underground supply flush complete, northwest underground supply will flushed at a later date.
INSP-Sprinkler Rough-in/Hydro4/8/20164/11/20164/11/2016ACANC
DetailsJim Page
Called point of contact, Jeff phone number ###-####, inspection request cancelled by Jeff due to issues with underground holding pressure, inspection request will be rescheduled for later date.
INSP-Sprinkler Rough-in/Hydro4/7/20164/8/20164/8/2016PCANC
DetailsJim Page
Jeff is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro4/7/20164/8/20164/7/2016ACANC
DetailsJim Page
Please schedule the underground hydro with Jeff. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in3/18/20163/18/20163/18/2016PPASS
DetailsJim Page
Rough to cover inspection complete for underground supply, underground piping approved for cover.
INSP-Sprinkler Rough-in3/17/20163/17/20163/17/2016PCANC
DetailsJim Page
Inspection request cancelled per conversation with Bryan, concrete would not be delivered before end of business day, contractor will reschedule inspection request.
INSP-Sprinkler Rough-in3/15/20163/16/20163/16/2016APART
DetailsJim Page
Partial rough to cover approved for underground supply mains, holes were still being cored in the footing for the stub in to the building at tine of inspection. Cover is approved up to the 90 degree fittings for the stub in, contractor will schedule inspection for complete cover when thrust blocks/piping is installed for stub in through footing.