INSP-Final Inspection | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Final Inspection | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PART |
Jim Page
|
|
|
Simplot headquarters building is complete, annex building is complete, permit will remain in issued status until courtyard/plaza level where hose valves are located is complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic re-test for northeast main tower standpipe passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2016 | 12/27/2016 | 12/27/2016 | P | CANC |
Jim Page
|
|
|
Hydrostatic test rescheduled
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2016 | 12/23/2016 | 12/23/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with contractor, request will be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2016 | 11/21/2016 | 11/21/2016 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for standpipes was completed on 13JULY2016 (FIR15-00602 this was the FIR permit inspection that was requested) hydro test was included in with level 1 hydrostatic test due to standpipe being supplied by level 1 of main building. Activities note that was entered on 29AUG2016 hydro request (noted under FIR15-00602) was for level 1 and 2 of annex.
|
INSP-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PART |
Jim Page
|
|
|
Partial final for dry standpipes complete, all dry pipe valves associated with the dry standpipes have been tripped for proper valve operation. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
|
INSP-Final Inspection | 10/17/2016 | 10/17/2016 | 10/17/2016 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 18OCT2016
|
INSP-Sprinkler Rough-in | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PART |
Jim Page
|
|
|
24 hour air test for dry systems associated with this permit started at 11:00AM (Total of 7 dry systems in test for 24 hours)
|
INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for hardlids located on level 5 annex complete, overhead fire sprinkler piping located above hardlids approved for cover.
|